Residential and non-residential construction
From old office to contemporary short-stay hotel
Text Liliane VerwooldePhotography Aannemersbedrijf G. Bruijnes

In the heart of The Hague, an old office building was transformed into a trendy new short-stay hotel with 37 short-stay units. The project involved installing entirely new façades, several rooftop extensions, a lift and a new balcony.
Anyone with even a passing interest in the execution of construction projects will see immediately that Aannemingsbedrijf G. Bruijnes faced a challenge here. The only way to create a construction site for the conversion of the office building on the Buitenhof was to cordon off part of the square in front of it. This provided the basis for stripping the building back to its load-bearing structure and then rebuilding it.

Limited space
“The logistical challenge was indeed considerable,” says Peter Feijen, project manager at Aannemingsbedrijf G. Bruijnes. “Given the amount of lifting work, we had to use a tower crane. Due to the lack of space, it had to be installed on the roof. This also had to be done in the middle of the night, as that was the only time the power supply to the tram line running past could be switched off. We also had two restaurants in the building, one on each side, which continued operating during the construction work. The logistics were a real puzzle.”
Lockdown
The coronavirus lockdown, which forced the two restaurants to close temporarily, worked in their favour. During this period, Bruijnes installed the drainage above the restaurants’ ceilings for the first and second floors. The lockdown meant the team could drill through the floor slabs without disruption. Bruijnes had finished this work just as the lockdown was lifted.
Varied façade construction
The façade was rebuilt using timber-frame walls, fitted with concrete façade elements and aluminium window frames. The concrete elements were installed first on each floor so that the frames could be fitted to them. Feijen says: “There was no room to change the sequence, even though the work was being carried out by different subcontractors. This called for consultation and tight scheduling. On the other hand, connecting the building to the neighbouring properties required creative solutions.”

Lift shaft extension
The tower crane, which was still on the roof, also made extending the lift a challenge. Before the renovation, the lift only went up to the fourth floor, but it now had to be extended to the fifth. “The tower crane was standing exactly where the lift extension had to go,” says Feijen. “We first dismantled the old lift, then removed the crane and built the lift extension. This was a real setback for our staff. They went without a crane or lifts for weeks and had to use hoists and mobile cranes to get the materials into position.”
Feijen is positive about the result. “The building’s original colours and lines have been retained on the outside. Inside, the entrance, apartments, corridors and large apartment on the fifth floor have all turned out beautifully.”
Question about this story? Ask your question
Who worked on Short Stay Hotel
- aluminium exterior framesLieftink GeveltechniekMentioned in Aluminium external frames: Glazed before installation
- ClientPorta KorzaIn this story
- ArchitectMBW ArchitectenIn this story
- Structural engineerIMd Raadgevende ingenieursIn this story
- ContractorAannemingsbedrijf G. BruijnesIn this story
- Façade elementsMGB Cladding SystemsIn this story
- FinishingEilers AfbouwIn this story
- Mechanical services contractorPonsioen InstallatietechniekIn this story
- Electrical contractorIGHIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectShort Stay Hotel
- SubjectResidential and non-residential construction
- CompanyPorta Korza
- CompanyMBW Architecten
- CompanyIMd Raadgevende ingenieurs
- CompanyAannemingsbedrijf G. Bruijnes
- CompanyMGB Cladding Systems


















