Construction projects

Everything for the softest drinking water

Text SlimmeZImage Walter Frisart

Everything for the softest drinking water

New build and expansion of Vitens in Epe

The softest drinking water in the Netherlands? It comes from Epe, where Vitens abstracts and treats water before pumping it to customers in the region. Salverda Bouw was tasked with renovating and expanding this drinking water production site without leaving households and businesses without water. 

In the water extraction area in the beautiful woodland of De Dellen, on the Gelderland Veluwe, there are eight large wells. They pump groundwater up from depths of 26 to 82 metres. The water is the softest in the country because the soil contains very little lime. The water is also naturally very clean: the sandy soil effectively filters it already. Vitens’ drinking water site in Epe ensures that this soft water flows from the taps of its customers.

The building blends into its wooded surroundings thanks to its gently sloping green roof. (Image: Walter Frisart)

To ensure water supplies could continue to be guaranteed in the future, the 1980s drinking water site needed a major renovation and expansion. Main contractor Salverda Bouw began work on this multi-year project in September 2022, working with Rook Pijpleidingbouw on the water-side installation work and Hollander Techniek on the electrical installation and process automation. The three companies are a familiar team, having worked together successfully on Vitens projects before. With a new pumping and control building, a fourth filter tank, a sludge thickener and a new electrical room in the filter building, the site will be fully prepared for the future. 

Not a day without water 

The water supply could not be interrupted during the works, which was the biggest challenge for the construction team. Water had to keep flowing from users’ taps, regardless of the work underway. Rick Maljaars, project manager at Salverda Bouw: “The project required a great deal of coordination to fit the many conversions into the existing operations. Because the new pumping building was to be built in a different location, everything had to be overhauled without interrupting the production process.”

For Hollander Techniek, which was responsible for the electrical installations, this was also a challenge, says project manager Franck de Bruine. “Before we can switch over completely to the new pumping building, the old and new buildings also need to operate alongside each other for a while. To make this possible, we had to map out the old installation thoroughly so we could connect to it. We then had to design various configurations, lay new cables and install new distribution boards and control cabinets.”

The building has a circular form, with timber cladding and a green roof. (Image: Walter Frisart)

A fine example of concrete work

For Salverda Bouw, a key part of the project was constructing the concrete basement tank in the pumping building, where the eight pumps send water to customers. Maljaars: “Working out how the basement tank should be designed, including the formwork and reinforcement, was an interesting job for our concrete construction team.”

A ‘green’ design 

Maljaars also found the distinctive design of the new pumping building an interesting aspect of the project. “It could have been a square box, but Vitens wanted the building to blend into its wooded surroundings. That’s why it has a circular form, with timber cladding and a green roof. The timber cladding is made up of substantial beams measuring 8 by 20 cm. We had to think carefully about which type of sustainable timber would be most suitable, how to fix the beams, how to make the whole structure watertight and how to ensure it could be maintained properly over time. These are enjoyable construction challenges that let us demonstrate our expertise.”  

Bat hotel and red lighting 

Respecting the existing flora and fauna was very important to Vitens on this project. That is why it had a bat hotel built into the earth bank at the new pumping building. Maljaars: “We worked closely with Vitens’ ecologist to establish exactly what this new home should look like.” He laughs: “It’s something different: as a construction professional, thinking about how bats like to live.”

De Bruine also learned something about the animals of the Veluwe woodland when it came to the electrical work. “The streetlights we were going to install had to be wildlife-friendly. Apparently, white light scares animals away. The ecologist told us that bats like red light and wild boar prefer green light. So, what were we to choose? In the end, we went with red light because there are no wild boar on the site.”

A basic necessity

From flora and fauna, we move on to another important aspect of this project: the security of the drinking water site. Many households and businesses depend on water from Epe. Since water is a basic necessity, the security requirements for sites like this are becoming increasingly stringent. Hollander Techniek has contributed to security in several ways, explains De Bruine. “As well as a fire alarm system, we installed a gas fire suppression system. If a fire is detected, gas is released to lower the temperature and extinguish the flames. If the power fails, a large emergency generator ensures that water production can continue as normal. In the event of a lightning strike, an earthing system prevents a fire from breaking out, while in the event of a short circuit it diverts the electrical current.”

Securing the building and network 

Hollander Techniek also delivered effective security solutions, working with a subcontractor. “As a drinking water facility, the site has to meet certain standards set by the National Coordinator for Security and Counterterrorism. This covers not only the security of the building itself, including who has access to which areas, but also, for example, protecting the network from hackers.”

Testing, testing and testing again 

In addition to the electrical installations and security, Hollander Techniek was also responsible for the software for this Vitens site. “This software controls all the systems, including those for the pumps and filters. It also ensures, for example, that the emergency generator starts up if there is a problem with the mains power.” Naturally, the software is tested extensively before being put into use. This is always a tense moment, because a great deal of time and effort has gone into all the systems. De Bruine: “When everything turns out to be working, it’s a fantastic moment. Especially because you’re working on something as crucial as a water supply, and you know what the consequences could be if things go wrong. That gives the work an extra dimension.”

The final stages 

The new pumping and control building is now complete, and the filter building has been fitted with an additional filter tank and a new plant room. The new sludge thickener further concentrates the waste filtered out of the water, meaning Vitens has less waste to dispose of. The construction team is working until May to transfer the eight pumps from the old building to the new one, one at a time. “Each pump has to be dismantled, transferred, installed and tested. We spend around three to four weeks on each pump. 

There is some pressure to get this done, as all eight pumps have to be transferred before the peak season, when water use increases. Fortunately, Vitens planned the process carefully in advance, and we are on schedule,” says Maljaars. 

A toast to a successful partnership 

Once the pumps have been transferred, all that remains is to demolish the old pumping building and landscape the site with paving and planting. Completion is scheduled for October this year. After that, all the parties can raise a glass to a successful partnership. Maljaars: “Vitens likes working with this combination of three contractors, and we at Salverda couldn’t agree more. Hollander Techniek and Rook Pijpleidingbouw are highly skilled companies with excellent reputations. The collaboration runs very smoothly. We share the same approach to a project: we simply want to do the job well.” De Bruine agrees: “I find the collaboration between Vitens, Hollander Techniek and Salverda very open and constructive. When something goes wrong, we help each other.”

Question about this story? Ask your question

Who worked on it

  1. ClientVitens
  2. ArchitectureSweco ingenieursbureau, Rooding architecten bna en Firma Bart: landschapsarchitect
  3. ContractorSalverda Bouw
  4. System integratorHollander Techniek (e-installaties en procesautomatisering)

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction projects
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.