Distribution centres

A production hall without water or sewer connections

Text Roel van GilsImage DHG, Mike Eijkelenboom

Burgland Bouw realiseerde het pand (30.000 m2) volgens het Smartlog-concept van DHG, inclusief een opslaghal van ruim 3.000 m2.
Burgland Bouw realiseerde het pand (30.000 m2) volgens het Smartlog-concept van DHG, inclusief een opslaghal van ruim 3.000 m2.

Can an industrial production hall operate entirely without connections to the drinking water supply or sewer network? Absolutely. The new site of Nijhuis Saur Industries (NSI) in Doetinchem shows that this is technically feasible. The building is equipped with a water-neutral system. Burgland Bouw was responsible for construction in line with DHG’s Smartlog concept.

NSI developed the water-neutral concept in collaboration with its project partners. It was designed with a view to future use in other buildings, with components of the system set to be modularly integrated. This makes the facility not only a functional part of the building, but also a reference project for similar sites, where water availability is becoming an increasingly important consideration.

Although Smartlog was developed primarily for logistics operators, the concept proved flexible enough to accommodate an advanced production environment. (Image: Mike Eijkelenboom)

A Smartlog development with specific requirements

Burgland Bouw delivered the building (30,000 m2) in line with DHG’s Smartlog concept, including a warehouse of over 3,000 m2. The collaboration between NSI and DHG began with a need to bring activities spread across four sites together in one central location. “Having our operations spread out created logistical challenges,” says Barry Domhof of Nijhuis Saur Industries. “So we looked for a central site in the region.” Suitable building land proved scarce. “We started looking into whether a new build could be developed on the existing site. However, the landowner was unwilling to sell. So we looked for a partner who could manage the development and reach an agreement with the owner. We found that partner in DHG, partly because the landowner had completed previous projects with DHG.”

The keys were handed over on 5 January 2026. The machinery, storage systems and building services are currently being installed. (Image: Mike Eijkelenboom)

Build-to-suit

An initial meeting outlined what might be possible. “After discussions with the landowner, we eventually managed to secure a 75-year agreement,” says Erik van der Woude, project manager at DHG. A 20-year lease was agreed with NSI. From that point, the plan was developed further in line with the Smartlog concept. “Although Smartlog was developed primarily for logistics operators, the concept proved flexible enough to accommodate an advanced production environment. The project was fully configured on a ‘build-to-suit’ basis, incorporating specific tenant requirements that can easily be adapted to a standard logistics hall when NSI leaves.”

Water-neutral

A key feature of the new site is its water-neutral system. It creates a natural water cycle, allowing the building to operate without connections to the drinking water supply or sewer network. Rainwater is collected in an underground reservoir and treated in the purification room to produce drinking water, which is used for showers, handwashing and other facilities. Domestic wastewater is extensively treated and reused for toilet flushing. Surplus treated water is infiltrated into the ground, helping to replenish regional groundwater reserves. The rainwater storage capacity is designed to provide enough water not only for drinking and sanitation, but also for the sprinkler system. 

Sustainable choices

Sustainability was central throughout the project. The building achieves a high BREEAM rating (Excellent), with attention paid to biodiversity, water management, material use, machinery and the fit-out of the production facility. For example, the storage racking is made from recycled ‘green steel’. Sustainable choices were also made in the energy strategy, although full energy neutrality is not yet achievable due to grid congestion. Provisions have, however, been made to enable off-grid operation in future wherever possible. 

Departing from the standard

Burgland Bouw was responsible for construction and for incorporating the tenant’s building requirements. “We know DHG’s Smartlog concept from previous projects,” says Dennis Mentink, project manager at Burgland Bouw. “Even so, the building differs from a standard logistics centre in its structure and layout. The necessary provisions have been made for the overhead cranes. The steel frame has been reinforced, and the mezzanine floors have been built at a lower level to create office space and work areas. In addition, some of the storage systems pass through the floors, which required further structural modifications.” 

According to Mentink, construction also presented challenges, particularly at the outset. “During the demolition of the old buildings, two explosives were found, which led to a temporary halt to work. The wet winter conditions also made it harder to get started. The water-neutral infrastructure was installed during construction, although the original aim had been to complete this during the foundation phase. Even so, we managed to deliver the project within twelve months.” The men say the success was mainly due to rapid decision-making, clear communication and maximum flexibility from all parties. The keys were handed over on 5 January 2026. Since then, NSI has been installing the machinery, storage systems and building services. The first relocations are due to start in April, and the site is expected to be fully operational by the summer. 

Question about this story? Ask your question

Who worked on it

Productiehal Nijhuis Saur Industries Doetinchem in Doetinchem

  1. developmentDHG

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectProductiehal Nijhuis Saur Industries Doetinchem
  • SubjectDistribution centres
  • CompanyDHG
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.