A quarter kilometer distribution center. Building from left to right.

A quarter kilometer distribution center. Building from left to right

Most distribution centers have the shape of a solid rectangle. The distribution center for AFL Barendrecht, on the other hand, is also elongated; 250 meters by 46 meters. This has consequences for the execution.

As an international transport company in fruit and vegetables, AFL Barendrecht was looking for a new distribution center. To realize this, they knocked on Hercuton's door. Not only to realize a suitable building, but also for support in financing. "Together we reviewed all the possibilities," says Jack van den Broek, Commercial Manager at Hercuton. "We ended up with the full rental of a new custom-built commercial building."

Impressie 1
A size of 250 meters by 46 meters has implementation implications.

From left to right

The custom-built building for AFL includes a refrigerated warehouse for storage and transshipment with an area of 12,000 m2, a repacking department and office space for rent, a mezzanine floor of 4,000 m2 and an office for AFL itself. And all in an elongated building volume, with the office centrally located on the first floor. "This had quite a few logistical implications," explains project manager Maikel Monde. "As a rule, you build from back to front, preferably planning the construction of the office as early as possible in the building process. After all, this usually requires the most finishing work." 

A complex whole

After intensive puzzling, the solutions presented themselves. With a left-to-right approach, the technical area - containing the installations for the refrigeration and freezer cells and the main distribution box for the hall's electrical system - is realized relatively quickly. The mezzanine floor is replaced with a closed floor, and large cutouts are made in two places in the floor to accommodate the goods/pallet elevator. Monde: "This is it in a nutshell, but the complexity is great. Just think about what you have to take into account in terms of safety when the recesses are made in the upper floor, while all kinds of work is also taking place downstairs." Extra attention is being paid to the Rc value and airtightness of the building to keep the generated cold inside later. For this purpose, the docks and levellers will be placed outside the front facade in detached dock houses.

Impressie 5
The office is centrally located on the first floor.

BREEAM 'Excellent'

Because of the high sustainability ambition - the BREEAM 'Excellent' certificate - Hercuton chooses sustainable, circular materials and applications. The installations will be ultra energy efficient, energy will be generated by solar panels, LED lighting will be equipped with motion sensors and the concrete will be (partly) circular. "These are some of the many environmental measures. Working to the standards of a BREEAM certification is now a very familiar route for us."

B7ABA6B0 3F8C 407B AB04 282D3C9FCA3C IMG 1544
A period of rain can turn schedules completely upside down.

Safety on one

Completion of the distribution center is mutually scheduled for Aug. 1, 2024. As things stand, that is feasible. But Monde would like to add a caveat. "No matter how carefully you plan, a period of rain, frost or storm can turn that schedule completely upside down. We then examine with the subcontractors whether we can perhaps work smarter or differently to meet the schedule. Of course, only if safety is guaranteed."  

20231103 134836
Most distribution centers are shaped like a solid rectangle. The distribution center for AFL is also elongated.
Construction Info
  • Client Garbe Industrial Real Estate GmbH, Amsterdam
  • Constructor, architect and contractor Hercuton, Nieuwkuijk
  • Installations Hoppenbouwers Techniek, Udenhout
  • Cooling Installation Paauw Industrial Refrigeration Solutions, Bodegraven
  • Construction period July 2023 - August 2024

"*" indicates required fields

Send us a message

This field is for validation purposes and should be left unchanged.

Wij gebruiken cookies. Daarmee analyseren we het gebruik van de website en verbeteren we het gebruiksgemak.

Details

Kunnen we je helpen met zoeken?

Bekijk alle resultaten