Distribution centers

Sligro | Deventer

Sligro | Deventer

At A1 Bedrijvenpark Deventer, Bouwbedrijf Aan de Stegge Twello B.V. is building a new distribution centre for foodservice wholesaler Sligro. The building meets Sligro’s requirements, has achieved a BREEAM ‘Outstanding’ rating and is being built to a tight schedule.

Better, faster and more sustainable go hand in hand in new-build foodservice wholesale centre

“We became involved in the project in the third quarter of 2018,” says Evert Veerman, commercial project manager at Aan de Stegge Twello. “Sligro wanted a consistent, nationwide approach. So we visited a number of previously completed Sligro projects as reference points. We then adopted the construction plans, adding value through our knowledge and expertise, the phasing of the work and 3D modelling of the plans.”

Design based on processes
Sligro Deventer has a floor area of 22,500 square metres. Designed by Omni Architecten, the building has a distinctive Sligro identity. “The design is primarily functional and based on the company’s processes,” says Veerman. “Sligro needs to manage chilled and frozen goods, dry groceries and packaging, alongside dispatch.” The building includes a 4,430-square-metre freezer, a 1,900-square-metre cold store, storage areas for dry groceries, an assembly area and a refrigerated, multifunctional dispatch area. There are also offices on the first floor, including workspaces and other areas supporting the business processes. The 39 loading bays are located at the front of the building.

BREEAM ‘Outstanding’
Sustainability is a guiding principle throughout the new-build project. Sligro deliberately chose A1 Bedrijvenpark Deventer, one of the greenest business parks in the Netherlands. Forty per cent of the park consists of water and green space, and it has no gas connection. Wind turbines along the A1 provide some of its energy. Veerman says: “Sligro’s building meets the requirements for BREEAM ‘Outstanding’. The foundation is smart, practical and efficient engineering. We are also incorporating tangible, proven sustainability measures, including high-performance insulation, LED lighting and modern, sustainable technologies. For example, the building is heated using waste heat from the refrigeration and freezing systems.”

Horecagroothandel Sligro

Short construction period
The construction phase is largely governed by the schedule. Handover to Sligro is planned for mid-2019. Working backwards, this meant that groundworks had to begin in mid-December 2018. “The contracts had not yet been officially signed,” says Veerman. “But we couldn’t wait. A week after the groundworks began, the piles were already on site, ready to be installed. The short construction period means we have to compress the schedule considerably and run activities in parallel. Together with our construction partners and Sligro’s suppliers, we are working to the lean method. We coordinate all activities seamlessly and hold a daily stand-up meeting each morning. This approach turns construction into assembly.”

Raising the bar together
The piles have been driven and the foundations laid, the steel frame is up, the cladding and roof are in place, and the floors have been poured. Inside the building, Aan de Stegge Twello is putting the finishing touches to the fit-out. Work is also progressing at pace on the landscaping. “Despite the tight schedule, the work is moving ahead well,” says Veerman. “That is partly thanks to the excellent collaboration, which raises the bar for everyone. We bring 45 years of construction expertise, while Sligro brings its experience from previously built branches. The great thing is that we can continue and strengthen this collaboration. We have now been commissioned to build Sligro Maastricht, and preparations are already well under way.”

Vraag over dit verhaal? Stel je vraag

Wie aan Distributiecentrum Sligro Deventer werkte

  1. BouwbedrijfAan de Stegge Twello B.V.In dit verhaal
  2. architectOmni ArchitectenIn dit verhaal
  3. vloerconstructieVan BerloGenoemd in Sligro | Optimisations in floor design
  4. opdrachtgeverSligro Food GroupGenoemd in Sligro | Optimisations in floor design

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectDistributiecentrum Sligro Deventer
  • OnderwerpDistribution centers
  • BedrijfAan de Stegge Twello B.V.
  • BedrijfOmni Architecten
Deel dit artikel

Advertentie

Volgen op Stedenbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.