Pioneering with timber
Text Roel van GilsImage Slokker Bouwgroep

Timber construction sounds sustainable and logical, but it is only when you start working with it that you realise it is still in its infancy. You soon come up against limitations. Aesthetic requirements are not always compatible with technical performance. Slokker Bouwgroep experienced this first-hand when designing Robin Wood on Centrumeiland. The initial plan was therefore fundamentally revised.
“The Robin Wood project came across our desks in mid-2023,” begins Dennis Jansen, project manager at Slokker Bouwgroep. “The client won the tender for plot 1 on Centrumeiland, a creative hub, with a plan that placed a strong emphasis on timber construction.” By the time Slokker Bouwgroep joined the project team, a design based on modular 3D units was already in place. “However, that idea was financially unviable, partly because of the mismatch between the architect’s aesthetic requirements and the technical performance.”

CLT system
The load-bearing structure was therefore fundamentally revised, from modular units to a CLT system. From the second floor upwards, the building is constructed in CLT (Cross Laminated Timber), with a concrete plinth providing a solid base. “This change also resulted in a significant increase in lettable floor area,” says André Breg, project coordinator at Slokker Bouwgroep. “When modular units are stacked, you end up with double walls and floors.”
Timber beams and weatherboarding
Timber construction is the norm on Centrumeiland. “Timber façades are popular, but knowledge and experience are still limited,” says Jansen, speaking from experience. “Even so, the architect came up with a façade grid comprising timber beams combined with weatherboarding.” Rather than using chemically treated timber, with all its environmental impact, Slokker Bouwgroep looked for a natural alternative. It chose Azobé for the façade grid, a timber species that can naturally achieve fire class B. It is far from a standard façade timber, as Azobé is prone to warping. The challenge was taken on nonetheless.
Warping tests
Warping tests were carried out with specialist partners. “The beams were reduced in thickness from 40 to 30 millimetres, and extensively tested for their behaviour and fixings,” says Jansen. “We then made a conscious decision to use reclaimed Azobé from the Dutch market. Old timber has less internal stress and is therefore more stable. It is a form of urban mining that also fits perfectly with the project’s sustainability ambitions.”
Tigerwood
“We initially considered bamboo for the weatherboarding, because of its stability and fire resistance, but the client wanted natural timber,” Jansen continues. “In the end, we chose Muiracatiara from Van den Berg Hardhout, also known as Tigerwood because of its dark brown streaks.” Fire tests on the Tigerwood weatherboarding and Azobé beams showed that achieving fire class B for the system as a whole was not feasible. Working with consultancy Nieman, the team looked for an alternative solution that would provide equivalent performance, settling on extensive compartmentation of the façade. “Each façade element forms a separate fire compartment within the cavity, with fire barriers and intumescent graphite strips to prevent fire spread,” Jansen explains. “This prevents fire from spreading unchecked and gives the fire brigade more time to respond at each element. The approach was assessed and approved in close consultation with the municipality.”
962 timber-frame elements
The façade is fully prefabricated by Frank van Roij: 962 timber-frame elements, complete with aluminium flashings, glazing, railings and screens, arrive on site ready-made. “The building is being constructed without scaffolding,” says Breg. “The iconic Azobé façade grid will be installed at a later stage. First, the main structure is erected, after which the apartments are finished internally. The gallery grid is then installed and connected to the CLT structure using steel brackets. Careful sequencing ensures quality and safety.”
Acoustic considerations
Finally, Slokker Bouwgroep also ‘had to’ come up with a solution to prevent sound transmission, and even found inspiration in an article about HAUT in Stedenbouw. Jansen: “There is no standard ‘best practice’ for CLT floors in residential construction. In the end, we opted for a loose-laid layer of limestone chippings on top of the 200 mm-thick CLT floor. Services are incorporated into this layer. Above it are layers of rock wool insulation and a tacker board with underfloor heating, finished with 50 mm of anhydrite.”
According to Breg, what makes this project special is not just the timber structure or the unique façade grid. “It is the way we worked together, and the hospitality shown by other timber builders facing the same challenges. That was a pleasant surprise. It is a sign that the sector is pioneering and learning together.”
Question about this story? Ask your question
Who worked on Robin Wood
- consultancyNiemanIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRobin Wood
- SubjectModular construction
- CompanyNieman


















