Studying in fully equipped workspaces
Tekst Liliane VerwooldeFotografie Hesco Bouw

Esdal College recently moved into a robust building designed for young people with ambitions in technology.
To prepare pupils as well as possible for the future, many classrooms have been fitted out as real working environments, just like the ones they will encounter in practice later on.
The new Esdal College in Emmen was built on the site of the former De Muzeval theatre. It has three storeys, around 3,900 square metres of floor space, fourteen classrooms, a theatre and a restaurant. The latter two also have their own entrance, allowing them to be used by other schools. The classrooms are equipped for the study programmes in Services & Products, Hospitality, Bakery & Recreation, and Mobility & Transport.

Changes to the foundations
When Hesco Bouw began work on the foundations at the end of 2019, concerns were raised by the local community at one point. “Driving the foundation piles caused vibrations and sometimes even damage,” says project manager Anton Brinkman. “We then changed the piling route and matched the pile lengths at each position to the pile loads to achieve optimum bearing capacity. This kept disruption to an absolute minimum. Where necessary, we settled damage claims with local residents.”
Concealed building services
The theatre also called for ingenuity. The architect decided to conceal all the building services above the theatre. “The ventilation systems in particular required a lot of space,” says Brinkman. “To limit noise pollution for the surrounding area, we installed all the services on the theatre roof, screened by false façades. The theatre, complete with retractable seating, has been built to professional theatre standards. This means pupils can gain genuine practical experience.”

Textured brickwork
The dark brickwork of the external façades stands out, giving the building its robust appearance. To add interest to the façades, projecting piers have been incorporated in several places. Brinkman says: “The piers were prefabricated in sections, mostly one metre high, and then fixed in place with angle steel and adhesive. They make a real aesthetic contribution.” Hesco Bouw has now completed the school, and the classrooms are ready to be occupied. Once lockdown is over, pupils will be able to get to work together.
Project details
Client Stichting Esdal College, Emmen
Project management ICS Adviseurs, Zwolle
Contract administration WKBA, Mantgum
Structural engineer Raadgevend Ingenieursbureau Lievense, Eindhoven
Architect De Architectenwerkgroep Tilburg
Building services Pranger-Rossier Installaties, Dokkum
Contractor Hesco Bouw, Stadskanaal
Contract sum € 6.5 million
Construction period November 2019, November 2020
Project details
Complex structure for Esdal College in Emmen
Construction work on Esdal College in Emmen began in September 2019. The structure was completed in week 16 of this year. It was a complex structure, explains project manager Tom Oude Voshaar of Tasche Staalbouw. The company manufactured, supplied and installed the entire steel structure.
Tasche also handled the engineering, says Oude Voshaar, and was therefore involved in the project at an early stage. With 215 tonnes of steel, it is a substantial structure, and its connections required a great deal of thought. “For example, the structure includes 400 by 25 mm wind bracing flats, which are much heavier than usual. The fire safety requirements also called for a heavy structure.”
He explains that during the preparatory phase, the contractor and architect held extensive discussions about the structural design. The engineering work then resulted in a document of more than 600 pages. “Beams with HEA600, HEA700 and HEA800 profiles were used. They rest on tubular columns and box columns measuring 300 by 8, 250 by 8 and 220 by 8. This resulted in complex welded connections, which were then bolted together on site. As the columns were also filled with concrete, the bolted connections are more complex than usual. In addition, 5 different types of protective coating were applied.”
One challenge, says Oude Voshaar, was ensuring the right materials arrived at the construction site in each delivery at the right time. “We drew up a logistics plan in advance, and it worked very well. We worked in alternating stages: we installed the columns, the contractor poured the concrete, we placed the beams, and the contractor followed with the floors. Everything went according to plan, so we can look back on the project with satisfaction.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Esdal College in Emmen
- opdrachtgeverStichting Esdal College
- projectmanagementICS Adviseurs
- directievoeringWKBA
- constructeurRaadgevend Ingenieursbureau Lievense
- architectDe Architectenwerkgroep
- installatiesPranger-Rossier Installaties
- uitvoerderHesco Bouw
- staalconstructieTasche Staalbouw
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectEsdal College
- OnderwerpConstruction projects
- BedrijfStichting Esdal College
- BedrijfICS Adviseurs
- BedrijfWKBA
- BedrijfRaadgevend Ingenieursbureau Lievense
- BedrijfDe Architectenwerkgroep