Renewal without disruption

The technical heart of the Westknoop
Commissioned by BAM Civiel, Klaver Technisch Bedrijf delivered the complete electrical installation for the Westknoop, a key interchange within Amsterdam’s historic Central Station. The technical challenge was considerable: relocating and renewing almost all the high- and low-voltage installations without taking them out of service in the Westknoop, or even across the entire Central Station.
“Within our scope, we modified and renewed a large number of electrical installations, ranging from 230 to 10,000 volts,” says Arjan Pronk, project manager at Klaver Technisch Bedrijf. “Many of the cables and conduits ran along the ceiling above the platform. Since the platform was completely demolished along a length of around 80 metres, we first had to reroute all the cables and conduits along a temporary route through
the passenger tunnel.”
New plant room
The existing plant room also had to make way to allow the transfer area in the Westknoop to be widened. “We built a new one 20 metres further away, then disconnected the systems one by one and transferred them to the new plant room. It was quite a challenge, because many of the station’s installations were old and not always labelled, which meant a lot of searching and testing,” recalls Chris Bankras, work planner at Klaver Technisch Bedrijf. Critical installations, including fibre-optic cables, fire alarm systems and evacuation systems, also had to be relocated and renewed. The entire evacuation system at platform level was moved to a new room more than 100 metres away. Here too, the system had to remain fully operational throughout. But Klaver Technisch Bedrijf was well equipped for the task. “We have our own technicians and can respond quickly,” says Pronk. “We also have extensive experience with ProRail sites and renew stations throughout the country. We know ProRail and NS regulations, and we hold the Safety Passport for working safely alongside the railway.”
What made the project particularly remarkable, the two men say, was the combination of technical complexity, time pressure and safety. “Passengers continued to use the station throughout the works. That called for careful planning, night-time working and close coordination with all the parties involved.” A further 1.3 kilometres of LED lighting was installed during the finishing phase. “A great deal of attention was paid to aesthetics and finish.” The result: a renewed, future-proof technical heart and a station that has visibly improved, without passengers ever having to stop.
Een zakelijke vraag aan Klaver Fietsparkeren? Neem contact op
Wie aan Westknoop werkte
- bouwbedrijfBAM Infra NederlandGenoemd in Renewing the western passenger tunnel entrance at Amsterdam Central Station
- ontwerpArcadisGenoemd in Renewing the western passenger tunnel entrance at Amsterdam Central Station
- complete amovatie
Amovatiebedrijf AalsmeerGenoemd in Demolition work in full swing at Amsterdam Central Station
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectWestknoop
- OnderwerpConstruction projects
- BedrijfKlaver Fietsparkeren




















