Demolition work in full swing at Amsterdam Central Station
Text Frederique HutingImage Amovatiebedrijf Aalsmeer

Craftsmanship, timing and complete control
Amovatiebedrijf Aalsmeer spent a year and a half working through the layers of Amsterdam Central Station. Literally. The bulk of the demolition had to be completed in eight weeks. From removing the escalators on the platform to excavating the floor beneath them, every step called for craftsmanship, timing and complete control. More than 3,000 tonnes of rubble and soil were taken away by train, right through one of the busiest stations in the country.
The Westknoop is an important piece of the puzzle in the extensive renewal of Amsterdam Central Station. Reconfiguring the tracks, systems and platforms will create more space for passengers and infrastructure. Underground, space was cleared for future facilities, while above ground escalators, floor sections and structures were removed to make way for the next construction phase. Amovatiebedrijf Aalsmeer (AA Sloopwerken) was responsible for the complete demolition of the area, from preparatory demolition to earthworks.
Not demolition, but careful dismantling
“What we do is different from ordinary demolition,” says Laura Vijfhuizen, project manager at Amovatiebedrijf Aalsmeer. “Careful dismantling means removing things with due consideration. It is dismantling rather than breaking things up. Especially in a place like this, you have to take everything around you into account: historic features, passers-by, train timetables, … You cannot just go in with a sledgehammer.” With almost four decades of experience, the family business specialises in demolition in urban areas. “The whole Randstad is our area of operation, but Amsterdam is special. The city calls for finesse. You are working in a tiny space, but with a whole fleet of machinery.”


An escalator shaft as a gateway
The project began with an escalator weekend: a tightly scheduled window in which the existing escalators had to be disconnected and removed. The cranes and shovel were brought in by train, and the escalators were taken away the same way. “We removed the entire escalator structure in a single weekend,” says Vijfhuizen. “Then we lowered three cranes and five shovels through that opening in the platform. The shovels remained on the platform.” The machinery was deployed underground to remove concrete structures, excavate floors and clear rubble.
What was dismantled below was lifted out above. “We had a larger crane on the platform, with a sizeable boom. It lifted the rubble out. And everything that came out went on the train.”
Clearing the tracks without leaving a trace
For the first time in its history, Amovatiebedrijf Aalsmeer handled all deliveries and removals by train. The company would normally arrange this by road, using its own container service. “But that simply wasn’t possible here,” says Vijfhuizen. “So we made the most of every trip: whenever something was brought in, we took something out at the same time, and vice versa. Efficiency was the key.” Making the work possible required close coordination with ProRail. At the same time, the team worked to minimise disruption. “The platform was literally ‘cut’ so that vibrations would not spread to the surrounding offices,” Vijfhuizen explains. “And of course, we did a lot of work in the evenings, at night and at weekends. Our team put in a lot of extra hours, but everything ran smoothly. The preparation had simply been done properly.”
Working by hand alongside the historic fabric
Perhaps the most delicate work took place alongside the historic façade bordering the platform. “We sawed it completely free in advance,” says Vijfhuizen. “Only then could we begin dismantling, and the edges were finished by hand. The natural stone on the inside had to remain in place. That calls for craftsmanship and patience.” The choice of machinery also took this into account. “We worked entirely electrically in the underground areas. Not just because of the fumes, but also because we like to work sustainably.”
A start to be proud of
For Vijfhuizen, the biggest milestone was the start. “The first weekend went so well. The escalators came out, the machines went in, the rubble was lifted out: everything fell into place. I look back on it with real pride. And I’m proud of our people, who worked incredibly hard in an environment that was complex technically, logistically and structurally. It takes everyone pulling together.”
Work that is out of sight, but not out of mind
Much of the work carried out by Amovatiebedrijf Aalsmeer is now hidden from view. The escalators have gone, the floor has been renewed and the rubble removed. But look closely and you can see the signs of skilled workmanship: in the careful finishing, the preservation of the historic features and the fact that the station barely stopped operating during the works. “It is an iconic building,” says Vijfhuizen. “Everyone has a memory of it. Being able to work there made it all the more special.”
Een zakelijke vraag aan Amovatiebedrijf Aalsmeer? Get in touch
Who worked on Westknoop
- construction companyBAM Infra NederlandMentioned in Renewing the western passenger tunnel entrance at Amsterdam Central Station
- designArcadisMentioned in Renewing the western passenger tunnel entrance at Amsterdam Central Station
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectWestknoop
- SubjectHeritage construction
- CompanyAmovatiebedrijf Aalsmeer





















