Mastic asphalt makes platform walkable, waterproof and sufficiently slip-resistant
Text Roel van GilsImage SBO

The refurbished platform above the Westknoop has been finished with mastic asphalt, as has been customary for many years at Amsterdam Centraal Station. BAM Infra Civiel called on the expertise of SBO, based in Andelst. SBO delivered the complete platform floor build-up, including waterproofing from the concrete structure through to the final mastic asphalt surface.
SBO has extensive experience in laying mastic asphalt, particularly on complex projects. “Although we are a subsidiary of BAM, that doesn’t mean every project is handed to us on a plate,” says SBO’s Rody Eikelenboom with a laugh. “Our experience on previous projects had fostered a valuable connection between the work planners. That’s how we got involved in this project.”
Unique property
SBO’s brief was to apply a waterproofing layer to the newly cast concrete platform structure, followed by two layers of mastic asphalt. “The waterproofing layer consists of a special roofing membrane that bonds fully to the concrete substrate,” Eikelenboom explains. “This was followed by two layers of mastic asphalt, 5 centimetres thick in total, which was necessary to provide a waterproof finish and withstand the expected loads. The resulting floor finish is robust, waterproof and functional for passengers.” Contrary to what you might expect from such a smooth floor, mastic asphalt has the unique property, according to Eikelenboom, of remaining sufficiently slip-resistant in all conditions. “When the floor is wet, it actually becomes slightly more slip-resistant.”
Mastic asphalt dumpers
Looking back on the work, Eikelenboom says the tight schedule was the biggest challenge. “The work had to be completed quickly because the station was already partly in use. The logistics were complex, particularly because of the lorries, lifting equipment and mastic asphalt dumpers needed to transport the asphalt to the platforms. The wheeled dumpers also had to operate below full capacity because of weight restrictions on the platform deck. There were a lot of pieces to fit together to bring the project to a successful conclusion, and we managed it. Although it is impossible to replicate the classic appearance, over time the floor will come to look similar to the other platforms. We also went on to build platform 6 for BAM Infra Civiel. While that was not part of the Westknoop project and had a different structural build-up, the finish is ultimately identical.”
Question about this story? Ask your question
Wie aan Westknoop werkte
- construction companyBAM Infra NederlandMentioned in Renewing the western passenger tunnel entrance at Amsterdam Central Station
- designArcadisMentioned in Renewing the western passenger tunnel entrance at Amsterdam Central Station
- complete demolition
Amovatiebedrijf AalsmeerMentioned in Demolition work in full swing at Amsterdam Central Station
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectWestknoop
- SubjectGeneral