Renovation transformation

Badhotel | Scheveningen

Badhotel | Scheveningen

In just three weeks, Badhotel Scheveningen was fitted with new window frames and windows in January this year. The short construction period was not the only challenge: almost every window opening was a different size. “The team delivered a fantastic performance.”

Faultless window-frame renovation at Badhotel Scheveningen thanks to meticulous teamwork

‘Every step planned and reviewed down to the half-hour’

Dekker Kozijnprojecten was selected to carry out the work. Project managers Piet van den Berg and Ivo Middeldorp say it was clear from the outset that this would be a challenging project. “The enquiry came in October, and the project had to be completed in January, at relatively short notice. The hotel was closing during the works, and January is its quietest period.”

That meant there was no time to lose: the openings had to be measured, and the materials then ordered. The survey quickly revealed that the building, in a protected townscape, is extremely uneven. “No two window openings are the same, with differences of up to 14 centimetres,” Van den Berg and Middeldorp explain. “But of course, you shouldn’t be able to see that in the finished result. We addressed it by using setting frames in different sizes. In the end, 89 different types of setting frame were used for the 102 windows. Every opening was carefully measured from a suspended work platform. The measurements were then entered into an Excel spreadsheet, giving us a clear picture of the differences.”

Barth Installatietechniek realiseert alle elektrotechnische, werktuigbouwkundige en sanitaire installaties in het nieuwe en hypermoderne distributiecentrum.

Another challenge was that the work could not run behind schedule. The hotel was due to reopen after three weeks. “And in January,” says Van den Berg, “when you can get all sorts of weather. So we decided to work from scaffolding rather than use cranes. The scaffolding was fitted with wind-reducing mesh and rainproof covers.” Then there was the logistics: getting all the materials to the right place at the right time so they could be installed without delay. That, too, was prepared down to the last detail, Middeldorp explains. “We planned and reviewed every step down to the half-hour. We made mock-ups of components in the workshop and practised with them, so we could work out how to install them effectively on site. We then prepared everything in the workshop so that it could be delivered to the site in Scheveningen quickly and in the right order.” Middeldorp and Van den Berg praise the commitment of everyone involved. “The fact that everything went smoothly was down to a fantastic team effort. The collaboration with the people at Badhotel Scheveningen was excellent, too. They gave us every assistance, and nothing was off the table.”

Badhotel

Thea van de Koppel, interim manager at Badhotel Scheveningen, shares the same positive feelings about how the project and collaboration went. She was closely involved throughout on behalf of her employer Metterwoon, the hotel’s owner. Alongside Metterwoon’s requirements, the municipality was also keeping a close eye on the work, she says. “Because it’s in a protected townscape. It was important to us that the window frames had a look that suited our corporate identity, in this case Metterwoon blue combined with white concrete. The windows needed to provide both sound and thermal insulation. We wanted more daylight in the north façade, so part of the stairwell façade was cut away. And we did indeed request that the project be carried out in January, over three weeks. That was the most convenient time for us.”

Van de Koppel says she is very pleased with how everything went. “Dekker delivered on what they promised. They monitored the schedule closely and stepped in wherever there was a risk of delay. That shows how flexible they are. There was also constant, close consultation, and they kept us informed about everything. Towards the end, they handed over the work in stages, from the back to the front and floor by floor. That gave us the opportunity to get the hotel ready in time for the guests who had booked for the end of January.”

Vraag over dit verhaal? Ask your question

Wie eraan werkte

Badhotel Scheveningen in Scheveningen

  1. kozijnenrenovatieDekker Kozijnprojecten
  2. eigenaarMetterwoon

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectBadhotel Scheveningen
  • OnderwerpRenovation transformation
  • BedrijfDekker Kozijnprojecten
  • BedrijfMetterwoon
Deel dit artikel

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.