Custom-designed installation preserves the aesthetic character of Theater aan de Parade
Text Ramona KezerImage Marc Vunderink, SPIE

Electrical and mechanical installations, plus fire protection & security system
Various disciplines within SPIE Nederland worked together on the complete building services installation for the new Theater aan de Parade in the city centre of Den Bosch. For each element, ‘invisible’, bespoke solutions were chosen to preserve the theatre’s aesthetic. “It is a complex and challenging building in which to install building services.”
Main contractor Mertens Bouw approached building services contractor SPIE during the tender phase to contribute to the design and pricing of the technical installations. Together, the companies designed the entire project in BIM 3D. Son Huynh, SPIE’s project manager for the electrical installation, says: “A technical design had already been prepared by an external consultant, and we developed it further. We made a number of changes along the way. A 1,600 kVA transformer had been specified, for example, but our calculations showed that at least 1,750 kVA was required. In the end, a 2,000 kVA transformer was installed in the theatre basement.”
Installing such a large transformer inside a building is unusual. In this case, there was no alternative because of the limited space in Den Bosch’s city centre. Getting the enormous transformer inside was quite a job, Huynh explains. “In the end, the transformer was partially dismantled for transport and then reassembled in the basement. The power calculations required a lot of research during the preliminary phase, as well as extensive consultation with various consultants.” Alongside the standard components of the electrical installation, the theatre also features some unusual elements: DALI/DMX/Art-Net and luminaires with dim-to-dark functionality to create the desired atmosphere, scenes and lighting levels. The challenge was getting these systems, each with its own protocols, to communicate with one another.

Complex building
Libert Huinen, SPIE’s project manager for the mechanical installation, says the theatre is a relatively complex building in which to install building services. “Transport, logistics, storage and coordination with all the other disciplines were a major challenge in the limited space in the city centre. We were working alongside various subcontractors, so the site was very busy. Bringing in large items of equipment such as air handling units, heat pumps and dry coolers was challenging.” The project uses an aquifer thermal energy storage system with two boreholes: a heat source in the Casinotuin and a cold source on the Parade, both drilled to a depth of 80 metres. This primary system is connected to the secondary system, which includes 20 underfloor heating manifolds connected to 18 km of underfloor heating pipe. There are also climate ceilings in a range of colours. Huinen says: “The largest air handling units are concealed in the roof. To preserve the building’s aesthetic, the pipework, control and instrumentation cabling, and ductwork are all hidden from view.”

On-site water storage
Mark Mommersteeg was project manager for the theatre’s sprinkler installation, representing the Fire Protection & Security discipline. “The sprinkler system is equipped with an electrically powered pump and draws on an on-site water supply of 160,000 litres beneath the theatre. All components of the sprinkler system are concealed. Gold-coloured sprinklers have been installed in the gold-coloured ceilings, for example. Even the fire detectors are finished in the same colour as the surfaces on which they are mounted.” This is bespoke work, particularly given the wide variety of ceiling and wall finishes throughout the building.

Fire tests
Huub Luijten, project manager in SPIE’s Security department, was responsible for all the theatre’s fire and security systems, comprising intruder detection, access control, a camera and intercom system, a fire alarm system and an evacuation system. Luijten says: “The evacuation system is a type A system with voice alarm. In an emergency, visitors are instructed in various languages to make their way to the exit. We used different systems in different areas because every space is different. The auditoria, for instance, have high ceilings and therefore require different types of smoke detector. Some performances also use smoke machines or fireworks, and you don’t want the fire alarms to go off in those situations. We therefore use several types of high-quality, highly sensitive fire detector. The entire installation was then extensively tested using controlled fires. These tests had to take place well before the theatre’s building work was complete, to ensure the fire safety of the project.”


In short, this was a wide-ranging project in which SPIE’s various disciplines were able to make full use of their expertise. Close communication enabled the project team to work well together. The client had a single point of contact for the entire installation.
Question about this story? Ask your question
Wie aan Theater aan de Parade werkte
- main contractorMertens BouwbedrijfMentioned in Theater aan de Parade puts contractor in the spotlight
- main contractorMertens BouwIn this story
- full-service installerSPIE NederlandIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectTheater aan de Parade
- SubjectHVAC
- CompanyMertens Bouw
- CompanySPIE Nederland