Porta Korza, the client for the Short Stay Hotel, set a high bar for its climate control and plumbing systems. The apartments had to offer a high level of comfort in both summer and winter. They all had to be fitted with ventilation, underfloor heating and supplementary cooling. Ponsioen Installatietechniek managed to exceed these requirements by a wide margin.

First, Ponsioen Installatietechniek disconnected the building from the district heating network. By installing air-to-water heat pumps, it made the building self-sufficient. It then used waste heat from the cooling systems to provide the apartments with domestic hot water. Joost Koole of Ponsioen Installatietechniek explains: “Normally, excess heat in a building is discharged outside. At the Short Stay Hotel, we capture this heat and use it as a heat source for domestic hot water in each apartment. From an energy perspective, this is a very beneficial solution. First, it reuses heat. Second, domestic hot water is no longer circulated around the building 24/7, causing unnecessary heat loss and unwanted warming. Instead, waste heat is used whenever a resident turns on a tap.”

Each apartment has its own services cabinet.

Collaboration

Koole looks back positively on the project team meetings. “When everyone is working towards the same goal, that is when you find the best solutions. For example, together with the architect and contractor, we looked for the best location for the systems serving the apartments. They are now positioned so well that residents lose very little space as a result. There is another advantage too: the systems can be maintained from outside the apartments, so residents do not need to be there.” 

Logistical benefits

The project’s biggest pleasant surprise was the logistics. “To reach the site, everyone had to cross the tram tracks and then find their way to the site along a winding route. We anticipated so many problems that we considered picking up technicians in a shuttle bus. But in practice, everyone reached the site without any problems. The car park beneath the building also proved useful. We were able to park our company vans there.”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectHVAC
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.