Asbestos removal and demolition for renovation of apartment block in Utrecht
Text VlasmanPhotography Vlasman

Housing association Portaal has a complex of 174 homes on Nigerdreef in the Overvecht district of Utrecht. The apartment block has 10 storeys and dates from the 1960s. As the homes no longer meet today’s standards, a major renovation and sustainability upgrade programme is under way. The old kitchens, bathrooms and toilets are being replaced, and the homes are being made more energy efficient. The communal areas are also being given a contemporary makeover. Vlasman is working as a co-maker for main contractor BAM and is responsible for asbestos removal and the demolition of the building elements to be replaced.

Vlasman’s asbestos removal team is divided into an external crew and an internal crew. The internal crew tackles asbestos-containing materials in the meter cupboard and in the bathroom, kitchen and toilet. These include tile adhesive (5,300 m2), sealant, window sills (52), sheet material (110 sheets) and bitumen floor coverings (430 m2). Work in each home is carried out according to the level of contamination identified during the prior survey. Asbestos removal in each home takes an average of two days, during which residents are provided with temporary accommodation. The other crew works from outside. Using a mast climbing work platform, they remove the windows and then the asbestos-containing glazing sealant (22,000 m).

Once the homes have been cleared for work, the asbestos removal team makes way for its demolition colleagues. They remove the kitchen units, bathroom floor and sanitary fittings, and cut openings and channels where needed for the new installation. Meanwhile, outside, the façade panels on the side elevation are cut off and lifted away. Given the height of the apartment block, Vlasman uses a telescopic crane and a 35-metre scissor lift. The old lifts are also demolished, as are the entrance hall and the stairs at the entrance.

The 174 homes are spread across six stairwells. All work starts on the top floor and then proceeds downwards, one stairwell at a time in vertical sections. Coordination between the various co-makers is crucial, as their work has to be carefully sequenced. Time is tight because the apartment block remains occupied, and the schedule is demanding. Only one construction hoist is available for removing materials. Vlasman coordinates this process: the glass and window frames are set aside for reuse, while the remaining materials are removed in separate waste streams. Work began in March 2021 and is expected to take a year.

Asbestos removal and demolition for renovation of apartment block in Utrecht
• Extensive asbestos removal inside and out
• Demolition of bathrooms, kitchens and toilets, façade panels, lifts and communal areas
• High-rise work: use of a mast climbing work platform, telescopic crane and scissor lift
• Renovation while occupied, under time pressure
• Waste stream coordination: 250 tonnes of rubble, 150 tonnes of glass, 50 tonnes of asbestos
• Close collaboration with other co-makers
Question about this story? Ask your question
Who worked on it
Nigerdreef in Utrecht, renovation
- co-makerVlasman
- main contractorBAM
- Housing associationPortaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNigerdreef
- SubjectRenovation & conversion
- CompanyVlasman
- CompanyBAM
- CompanyPortaal