Renovation & conversion

Heritage and craftsmanship come together on Prins Hendrikkade

Text Lieke BousemaImage Heyligers

Het complex krijgt een nieuwe toekomstbestendige functie, die aansluit bij de dynamiek van de binnenstad én de groeiende vraag naar kwalitatieve werk- en woonruimte. (Beeld: Heyligers)
Het complex krijgt een nieuwe toekomstbestendige functie, die aansluit bij de dynamiek van de binnenstad én de groeiende vraag naar kwalitatieve werk- en woonruimte. (Beeld: Heyligers)

Renovation and sustainability upgrades with respect for the past

At Prins Hendrikkade 16-19 in Amsterdam, opposite Central Station, the former Beekwilder buildings are undergoing an extensive renovation and sustainability upgrade that respects their architectural character and cultural heritage value. From the third quarter of 2026, the distinctive buildings will provide space for a modern office environment and five high-quality apartments. This gives the complex a new, future-proof purpose that reflects the dynamism of the city centre and the growing demand for high-quality work and living spaces in one of the city’s most prominent locations.

New roof windows, glazed roof sections and ventilation and air-treatment systems are being integrated into the roofs.

The complex on Prins Hendrikkade comprises four connected plots dating from the seventeenth century and forms part of Amsterdam’s UNESCO World Heritage-listed city centre. The renovation therefore focuses on carefully preserving and restoring its historic character while meeting contemporary requirements for comfort, sustainability and functionality. Rijnboutt and Heyligers drew up the design in collaboration with Duyts Bouwconstructies, while Van Wijnen is responsible for the construction work. “We started work on site in the second quarter of 2025,” says Tobias Bolte, project manager at Van Wijnen. “By then, the strip-out and foundation repairs had already been completed. The layouts throughout the complex had been completely changed. A new concrete ground floor with service ducts had also been installed, preparing the building’s structural shell as far as possible for our work.”

Additional demolition work

However, this does not mean that Van Wijnen has only been building. “The rear façades of the front buildings were technically and aesthetically outdated and had no heritage value, so we demolished and replaced them entirely,” says Bolte. “We also replaced several flat roofs, removed old staircases and carried out extensive timber decay repairs.” He cites the historic structural floor beams, most of which will remain visible in the new interior design. “Only then could we start on the fit-out and interior package.”

New roof windows, glazed roof sections and ventilation and air-treatment systems are being integrated into the roofs.

Glazed bay window brings in more daylight

“One distinctive aspect of this project is that, after we had started the preparatory work, the client brought in Heyligers as interior architect,” says Bolte. “This led to far-reaching and extensive changes to the plans, as well as an application for an additional permit, which was not granted until December 2025. We had to adjust our schedule and work accordingly, but the added value was clear. For example, a change to the ground-floor plan between the rear and front buildings made it possible to create an outdoor space with a glazed bay window, significantly improving daylight penetration at the heart of the building.”

Work carried out in packages

To ensure sufficient structure, oversight and a clear division of responsibilities within the project team, the work was divided into manageable packages, Bolte explains. “First, we carried out timber decay repairs and reinforced the steel beams, followed by the complete demolition and replacement of the rear façades mentioned earlier.” In the new design, the rear façades of the front buildings have a timber-frame inner leaf and a brick-slip outer leaf, which was finished with Keim paint on site. “This creates a very good match with the existing listed front façades of the rear buildings.”

Restoration of the listed front façades

A third work package involved restoring the listed front façades of the rear and front buildings. “This involved not only timber decay repairs, but also the removal of all later additions,” says Bolte. “The lead and zinc were replaced, and all the timberwork was repainted. The front façades of two buildings were treated with oil again, while two others were given a fresh coat of Keim paint.” A new upper storey was also added to the rear buildings at numbers 16 and 19. “At number 16, additional living space was created by adding a pitched roof to a former flat roof. At number 19, a steel frame was installed for two heat pumps, complete with louvred façade cladding. The pitched roofs on all the front and rear buildings were then upgraded for energy efficiency. By retaining and reinstating the existing ceramic roof tiles, we preserved the historic roofscape.”

New lift shaft

The existing roof structures were also renewed and several flat roofs repaired. “Another interesting work package was the creation of an entirely new vertical circulation core in building 18, with a glass lift in a steel-and-glass lift shaft,” says Bolte. “A split-level dog-leg staircase was built around it.” The lift is unusual in that it is a through-car lift, making it possible to provide twice as many stops. “This means that most of the office complex can be accessed by lift.”

Van Wijnen recently installed a new ground-floor screed above the services, which had been fitted into the service ducts installed by the main contractor. “The fit-out packages in the offices and apartments are now also being completed, after which the restoration of the period rooms and the listed staircase will bring the renovation to a close.”  

Question about this story? Ask your question

Who worked on Beekwilderpanden

  1. roof renovationKorff DakwerkenMentioned in Historic roofing with modern precision
  2. clientVan WijnenMentioned in Historic roofing with modern precision
  3. designRijnbouttIn this story
  4. interior architectHeyligersIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBeekwilderpanden
  • SubjectRenovation & conversion
  • CompanyRijnboutt
  • CompanyHeyligers
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.