Distribution centres

5,000 m³ of concrete in the floors of Rotterdam DC

5,000 m³ of concrete in the floors of Rotterdam DC

Most of Rotterdam Polymer Hub has been fitted with a superflat concrete floor. As a regular partner of CONFERM, Van Berlo completed an extremely cost-effective floor in a very short time, meeting the specified flatness requirements. More than 5,000 m³ of concrete went into the project.

“At CONFERM’s invitation, we reviewed the various concrete floors in the new Rotterdam Polymer Hub distribution centre,” says Michiel van Zon, commercial and technical adviser at Van Berlo. “We share a great deal of knowledge and often look at possible design optimisations at an early stage. For this project, however, the floor design had already been finalised, so the main priority was to submit a competitive price. We were also working to a very tight schedule, as the completion date had already been set. ‘Lean’ planning was therefore essential.”

De banquetingruimte in de nieuwbouw is als doos-in-doos losgekoppeld van de woningen.

Van Berlo used around 5,000 m³ of concrete in the building’s floors.

Superflat and more

Rotterdam Polymer Hub’s distribution centre has a total floor area of 45,590 m². Van Zon: “More than half of that area, 27,500 m² to be precise, has been finished with our VB Exa® Superflat Floor, in accordance with DIN 15.185. The floor is ground-bearing. We followed the engineer’s detailed plan and did not need to call on our own engineering department. The floor was completed in 24 phases, using, among other equipment, our superscreed machine. In addition to this superflat floor for the narrow-aisle warehouse, we also built the other floors in the distribution centre. These comprise the floors in the so-called ‘bagging area’ (1,440 m²), the dispatch floors (5,490 m²), the office floors (600 m²), the mezzanine floor (4,200 m²) and the external loading bay pit structure (6,300 m²). In total, we used around 5,000 m³ of concrete in the building’s floors.”

Lean planning

Van Zon recalls that the project was under enormous time pressure from the outset. “The completion date had already been set. Given the scale of the project, that was quite a challenge. Good collaboration is essential to meet the schedule while also ensuring quality. All the conditions need to be right. We therefore drew up a lean plan in advance with all the parties involved, so that every activity fitted together perfectly. That worked well here. As mentioned, CONFERM is no stranger to us. We have already built several distribution centres of this kind together, and our collaboration is always very harmonious. We know what to expect from each other and can always work together to come up with the best possible solution. A solutions-focused approach is essential, particularly on projects of this scale. We are currently working with CONFERM on the construction of two more large distribution centres.”    

Have a business enquiry for Van Berlo | Experts in funderingen en bedrijfsvloeren? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectDistribution centres
  • CompanyVan Berlo | Experts in foundations and industrial floors
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.