A development process with its challenges

Technische Unie is building a new 7,500 m² business premises. The building at Westraven business park will bring together an office, shop, experience centre, training centre and logistics cross-dock under one roof.
‘We stayed on top of things from start to finish’
Borghese Logistics owned the land on which Technische Unie's new business premises is being built. It acquired the plot in 2015, and in 2018 a property agent put it in touch with several interested parties. Technische Unie's requirements and the available options appeared to be the best match. This resulted in a turnkey purchase agreement between Technische Unie and Borghese Logistics. “Once we have reached an agreement, our client can count on support from A to Z,” says Jelle Hogetoorn, property developer, Logistics, at Borghese Logistics.

The building overlooks the Amsterdam-Rhine Canal.
Requirements
Technische Unie had an extensive list of requirements. Its new premises had to serve as a transhipment hub for fine-meshed distribution to its customers and end users in the region. The building was to include a sustainability experience centre, office space and a training centre, while the roof, fitted with solar panels, also had to serve as a solar panel showroom. Hogetoorn says: “We then worked with TU and the architect to develop a design that met the full set of requirements.”
During this development phase, it soon became clear that the building would work best if divided into two sections: one for logistics operations and the other for the shop/showroom and offices. Once the preliminary design had been drawn up, Pleijsier Bouw was brought in to advise on the best way to build it.

The site is exceptionally accessible.
Complex operation
“The sewer installation was particularly challenging,” says Hogetoorn. “The site is beautifully located, right on the Amsterdam-Rhine Canal, but water drains away very slowly here. After consulting Hoogheemraadschap de Stichtse Rijnlanden, we opted for an infiltration sewer to carry the water to the pumping station. This was a major operation, both in terms of water engineering and road construction. It involved many specialists and required extensive consultation and coordination.”
Long lead-in time
“We develop a lot of distribution centres, usually on sites specifically designated for that purpose,” Hogetoorn continues. “But that was less clear-cut here. The building is also close to a hazardous materials storage facility, which required coordination with the municipality and province. The building's varied functions called for a long lead-in time. But construction began in early 2019, and we expect completion in spring 2020.”
Technische Unie will then be able to serve its customers even better. Several locations can be consolidated, access is excellent, the training centre has become more visible, and the experience centre demonstrates what is possible in sustainability. Hogetoorn says: “We are proud of the result. This building is an improvement to the area and adds value for Utrecht and the surrounding area. The building has a playful layout and fits in with its surroundings. Even the parking areas have a green appearance. One of our core values is that Borghese Logistics ‘stays on top of things’. We have lived up to that throughout this entire process.”