An XXL distribution centre built in just 6 months
Text Lieke van ZuilekomPhotography Batenburg Installatietechniek Monster

The modern XXL distribution centre on Zwarte Zeeweg, at Distripark Maasvlakte West, will provide 60,000 m² of lettable floor space, divided across four halls, each with its own office space. Working for main contractor De Vries en Verburg, Batenburg Installatietechniek Monster is delivering the mechanical and plumbing installations for the new build, based on the STABU specification prepared by installation consultant Valstar Simonis and in line with the building owner's BREEAM-NL ‘Very Good’ ambition.

The entire new build must be fully operational on electricity by final handover at the end of June. The climate control installations make an important contribution to this, says Wim Wigleven, Head of Projects at Batenburg Installatietechniek Monster. “The halls will be heated and cooled using air-to-air heat pumps combined with jet fans, which efficiently push warm air downwards and distribute the heat evenly. Halls A, B and C will each have two air handling units to supply sufficient fresh air. Hall D will have four air handling units. For the offices, we have opted for a carefully balanced combination of underfloor heating, VRF systems and air handling. In total, we are installing 14 air handling units and 78 heat pumps for this new build. On our advice, duo heat pumps were selected, with one outdoor unit for every two indoor units. This has significantly reduced installation time. In addition, the design optimisation has improved security of supply.” Wigleven praises Valstar Simonis for its open-mindedness, saying it was very receptive to ideas and optimisations as the design progressed from preliminary to final. “In consultation, we also chose a different type of air handling unit with a carefully designed control system, supplied by our regular supplier.”

Wigleven says the main challenge on this project is the schedule. “Construction began in mid-January, and the entire project has to be handed over by the end of June. To meet this tight construction programme, we have opted for flexible staffing. We have also significantly increased the workforce. At peak times, 10-12 installers were on site. Our installers and temporary staff have worked together to deliver the project. The result is a cohesive, hybrid team delivering both the mechanical and plumbing installations.” The plumbing installations include internal drainage, condensate drains for the heat pumps in the halls, hot and cold water systems in the offices, and all the toilet facilities.
Project details
Client
Dudok Logistiek Vastgoed
Architect
Designlogic, Nuenen and Adcom 2000, Rotterdam
Contractor
De Vries en Verburg, Stolwijk
Installation consultant
Valstar Simonis
Installations
Batenburg Installatietechniek, Monster
Question about this story? Ask your question
Who worked on DC Dudok
- Electrical installations and facilities
Van Hees Elektrotechniek & ICTMentioned in Sustainable, high-quality electrical installations - Project managementAdcom 2000 Architecten & IngenieursMentioned in XXL distribution centre on Maasvlakte II
- clientDudok Logistiek VastgoedIn this story
- architectAdcom 2000, RotterdamIn this story
- main contractorDe Vries en Verburg, StolwijkIn this story
- Building services consultancyValstar SimonisIn this story
- building servicesBatenburg Installatietechniek, MonsterIn this story
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectDC Dudok
- SubjectDistribution centres
- CompanyDudok Logistiek Vastgoed
- CompanyAdcom 2000, Rotterdam
- CompanyDe Vries en Verburg, Stolwijk
- CompanyValstar Simonis
- CompanyBatenburg Installatietechniek, Monster