DC bol.com: ‘Deformation requirements and floor levelness were our biggest challenges’

bol.com’s new warehouse in Waalwijk opens in 2021. The new distribution centre focuses on greater mechanisation and shorter walking distances for staff. With mechanisation a key priority, the engineers at flooring specialist Van Berlo had to take into account additional requirements for the levelness and deformation of the warehouse floors. We spoke to Glenn Verhoef, Commercial Director at Van Berlo.
Words | Roel van Gils Images | Van Berlo
The online marketplace’s new warehouse is already its second facility in Waalwijk. The first opened in 2017, but has already proved too small. “We installed the floors and foundations for contractor Van Wijnen in the first warehouse, which covered 50,000 m², and were invited back for the extension, this time by Bouwbedrijf Van de Ven,” says Verhoef. “The new warehouse also has a floor area of 50,000 m², but includes a section of mechanised high-bay storage.”

Van Berlo first poured 30 centimetres of concrete across the entire area, then added a further 15 centimetres on top.
Complex shuttle-system floor
Van Berlo’s work on the project comprised 24,500 m² of industrial floors, including the installation of 3,300 Mini Vibropalen, and 10,000 m² of dispatch floors underpinned by 1,900 Mini Vibropalen. It also involved applying 50,000 m² of topping to the upper floors and installing 14,000 m² of shuttle-system flooring in the fully automated warehouse. According to Verhoef, the flatness requirements for the fully automated warehouse were not particularly stringent. “However, we had to meet the so-called FEM standards for horizontal alignment and deformation. A floor can be level and still slope. It must also not deflect under the heavy loads in the racking. Neither issue is conducive to the optimal operation of the shuttle system.” The result was a floor 45 centimetres thick, designed to bear the loads imposed by the automated racking system, which uses shuttle systems at heights of up to 30 metres. “The concrete was poured wet-on-wet. In other words, we first poured 30 centimetres of concrete across the entire area, then added a further 15 centimetres on top.”

The floor in the shuttle-system warehouse.
In addition to the challenging shuttle-system floor, Van Berlo also drew on its expertise to install the toppings on the upper floors. “The upper floors were difficult to access during construction,” says Verhoef. “We had to pump the concrete over a considerable distance of 250 metres each time. This required careful coordination with the concrete supplier on the consistency of the mix. It had to travel that distance while still producing a good floor. In the end, everything went perfectly. Finally, we treated 37,000 m² of flooring with Ashford Formula, a sodium silicate-based concrete densifier that reduces dust and makes maintenance easier.”
Een zakelijke vraag aan Van Berlo | Experts in funderingen en bedrijfsvloeren? Neem contact op
Wie aan Distributiecentrum Bol.com Waalwijk werkte
- contractorVan WijnenIn dit verhaal
- contractorBouwbedrijf Van de VenIn dit verhaal
- kanaalplaat verdiepingsvloerenVBIGenoemd in 60,000 m2 of hollow-core floor slabs for bol.com’s new build
- staalbouwerVan den Brink StaalbouwGenoemd in 60,000 m2 of hollow-core floor slabs for bol.com’s new build
- advies, producten en servicesHoefnagels Fire SafetyGenoemd in Fire safety is the sum of advice, products and services
- constructeurPelecon structural engineersGenoemd in Bol.com’s second distribution centre is built to last too
- architecten- en ingenieursbureauDENCGenoemd in Bol.com’s second distribution centre is built to last too
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectDistributiecentrum Bol.com Waalwijk
- OnderwerpDistribution centres
- CompanyVan Wijnen
- CompanyBouwbedrijf Van de Ven
- CompanyVan Berlo | Experts in funderingen en bedrijfsvloeren



















