Clients and developers in the Netherlands continue to invest heavily in logistics warehouses and distribution parks. At Business Park 7Poort in Zevenaar, along the A12 and close to the German border, Goldbeck Nederland is building the first two warehouses of the G-Park logistics centre on behalf of developer Gazeley, providing a total floor area of 52,000 m². The remaining 130,000 m² plot will be developed in several phases in the future. Preparation and engineering began in summer 2019, earthworks started in October 2019 and the project is due for completion in early June 2020.
Gazeley, one of Europe’s largest investors and developers of logistics warehouses and distribution parks and part of global operator GLP, opened an office in Amsterdam in 2018. The company is currently involved, among other projects, in the redevelopment of a major logistics scheme in Venray. To meet growing demand for space in the Arnhem/Nijmegen region, the logistics property investor bought a 19-hectare plot in March 2019 to build the G-Park distribution centre. The new-build project is located on Business Park 7Poort in Zevenaar. It is strategically situated close to the A12 and A15 motorways and forms part of the well-known Logistics Valley. This region connects two of the Netherlands’ main ports, the Port of Rotterdam and Amsterdam Airport Schiphol, with Germany’s Rhine-Ruhr region. Goldbeck Nederland is building a mega-distribution centre on behalf of the developer. The family-owned company, with locations across Europe, its own engineering capability and a production facility for precast concrete, steel, aluminium frames and façade cladding, focuses on turnkey projects for logistics buildings, as well as business premises, car parks and office buildings.
First phase
“In the first phase, we are delivering a 52,000 m² logistics distribution centre, divided into two identical 26,000 m² warehouses that can be adapted to the requirements of one or more logistics service providers. To optimise the available storage space, the two units have a clear height of over 12 metres. The new distribution centre also has a total of 50 overhead doors, 141 parking spaces and high-quality office space,” says Vincent Vierwind, managing director of Goldbeck Nederland.

On behalf of investor and developer Gazeley, Goldbeck Nederland is building a 52,000 m² logistics distribution centre, divided into two identical 26,000 m² warehouses.
Project manager Krijn van Koolwijk adds: “We were awarded the contract in summer 2019 and immediately started engineering and drawing up plans for the foundations, precast concrete, concrete floors and steel structures. Following the earthworks, the first column was erected on site in November. All precast components are produced in our own factory, while the other building components, apart from the solar panels, are supplied in collaboration with several of our regular partners in the Netherlands and Germany.”
Renewable energy
Both warehouses are being developed to the BREEAM ‘Excellent’ standard. The low-maintenance complex will be ‘100% electric’, with rooftop solar panels supplying much of the required energy. High-quality LED lighting and innovative heating systems have also been selected. In addition, every effort is being made during construction to reduce CO2 emissions and energy and water consumption, use certified and recycled building materials, and make as much use of renewable energy as possible. “The buildings are due for completion by early June 2020, so they can be occupied in the third quarter of the year. Gazeley will then develop the remaining 130,000 m² of available lettable space in several phases,” conclude the managing director and project manager. “We are often involved in the delivery of distribution centres, but this is one of our largest projects at present.”
Question about this story? Ask your question
Who worked on it
G-Park in Zevenaar
- developerGazeley
Keep following this
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectG-Park
- SubjectDistribution centres
- CompanyGazeley