Distribution centres

Sustainable building services for Bleizo Logistics Centre

Text Lieke van ZuilekomImage Barth Installatietechniek

The Bleizo Logistics Centre in Bleiswijk.
The Bleizo Logistics Centre in Bleiswijk.

Construction is well underway in Bleiswijk on Bleizo Logistics Centre, a state-of-the-art distribution centre at a logistics hub in the heart of the Randstad.

The distribution centre will comprise approximately 43,000 m² of warehouse space, 2,700 m² of office space and 3,700 m² of mezzanine space, as well as 50 loading docks and around 300 parking spaces. The project is being delivered to BREEAM-NL ‘Very Good’ quality and sustainability standards. The building services installed by Barth Installatietechniek, part of the Barth Groep, make an important contribution.

As a subcontractor to Cordeel Nederland, Barth Installatietechniek is delivering all the electrical, mechanical and plumbing services at Bleizo Logistics Centre. “Following an intensive preparation phase, work began on site in mid-November,” says project manager Erik Lugtenburg. “For heat generation, we are installing two air-to-water heat pumps on the roof of the new building. The heating system in both warehouse sections (A and B) uses water-fired air heaters, while the office areas are fitted with underfloor heating. Combining the radiant heat from the floor with the rapid response of air heating (VRF system) ensures optimum comfort and minimal energy consumption. Each of the two office areas will have its own air handling unit, which will also be connected to a heat pump.”

Barth Installatietechniek is delivering all the electrical, mechanical and plumbing services in the new, state-of-the-art distribution centre.

The roof of the new building will be fitted with 148 solar panels. Barth Installatietechniek is also installing 20 EV charging points. “We have chosen LED lighting strips for the halls, and LED downlights and recessed fittings for the offices,” says Lugtenburg. “The fittings next to the windows will have daylight controls, enabling significant energy savings.” Each toilet block will have its own shut-off valve in the water system, linked to the lighting system. This will prevent water being wasted through leaking taps or continuously running toilets.   

Project information

Load-bearing floors in former polderland

The new Bleizo distribution centre in Bleiswijk is being built on a greenfield site in a former polder area, where the ground is far from load-bearing. This prompted main contractor Cordeel to outsource responsibility for both the industrial floors and the foundations to Twintec.

“The good, load-bearing sites in our country are pretty much built up,” says Jeroen Boers, Production Manager at Twintec. “More and more projects are moving to so-called greenfield sites, in other words former pastures with predominantly clay and peat soils, especially north of the major rivers. That is also the case with the new Bleizo distribution centre in Bleiswijk. Our challenge was not so much achieving the required flatness, but ensuring sufficient load-bearing capacity, and doing so during a ‘wet’ period (autumn). We therefore handled the entire process, from engineering and foundations through to construction of the Twintec Ultimate hybrid floors.”

Both the piling plan and the floor were designed to suit the ground’s limited load-bearing capacity, Boers continues. “We started piling straight after the 2020 summer holidays and will finish just before Christmas 2020. By then, we will have installed a total of 11,500 HiSpeed VSD piles, ranging from 15 to 18 metres in length. We will start work on the floors in January. Covering a total of 42,000 m², they are expected to be completed by mid-February. This is quite literally a high-pressure project.”

Project information

1,850 tonnes of steel

The new Bleizo Logistics Centre has a steel backbone. Commissioned by Cordeel, Hanse Staalbouw is designing, manufacturing and constructing the entire steel structure. No less than 1,850 tonnes of steel will be used. 

“We began detailed engineering in week 14 of this year and started producing the steel structure just before the summer holidays,” says Tim Hoek of Hanse Staalbouw. “By keeping production systematically ahead of schedule, we ensure that installation does not stall. We will erect the entire structure in just 12 weeks and complete it in early 2021.”

Since the ‘firma Hanse’ was founded in 1907, Hanse Staalbouw has grown into a recognised steel construction company and a household name in the building industry. “We specialise in steel structures for complete commercial buildings in the agricultural, industrial and non-residential sectors.”

Have a business enquiry for Twintec? Get in touch

Who worked on Bleizo Logistics Centre

  1. end investorMirastarMentioned in Bleizo Logistics Centre, Bleiswijk: Project under ‘high tension’
  2. end investorKKRMentioned in Bleizo Logistics Centre, Bleiswijk: Project under ‘high tension’
  3. architectPalazzo ArchitectenMentioned in Bleizo Logistics Centre, Bleiswijk: Project under ‘high tension’
  4. TIS agencyTechnische Inspectie ServiceMentioned in Bleizo Logistics Centre, Bleiswijk: Project under ‘high tension’
  5. electrical, mechanical and sanitary installationsBarth InstallatietechniekIn this story
  6. main contractorCordeel NederlandIn this story
  7. the complete steel structureHanse StaalbouwIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBleizo Logistics Centre
  • SubjectDistribution centres
  • CompanyBarth Installatietechniek
  • CompanyCordeel Nederland
  • CompanyHanse Staalbouw
  • CompanyTwintec
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.