The Netherlands’ largest distribution centre under construction

The Netherlands’ largest distribution centre is being built in Bleiswijk. The DC covers more than 140,000 m2, equivalent to around nineteen football pitches, and will be Europe’s most highly automated warehouse for the online retailer that will use it.
Demolition and construction take place at the same time
Every detail has been considered in the design of the distribution centre. The vast logistics centre will be functional, high-tech and sustainable. Its many large windows and high-quality climate control systems will also make it a pleasant place to work.
The logistics centre is a so-called ‘brownfield development’, built on the former FloraHolland site in Bleiswijk. The demolition of several existing commercial buildings freed up 22 ha of land for construction. In the new development, this will be divided into 100,000 m2 of operational floor space, 30,000 m2 of mezzanine floor space and 10,000 m2 of office space, all under one roof.
Hybrid structure
Because of the ground conditions, the DC is being built on more than 43,000 foundation piles. Work on the superstructure began as soon as the foundations for the first unit were complete. “We opted for a hybrid structure,” says Geert van Doorn of Aannemingsbedrijf Wouters Schijndel. “A combination of steel and precast concrete. The large spans and heavy loads on the mezzanine floor mean we are building that section in precast concrete. The rest is being built in steel for speed and relatively high flexibility. This allows us to build as quickly as possible and work cost-effectively.”

Large windows also make it a pleasant place to work.
Sustainability
The DC is being built to BREEAM Very Good standards. This target requires high-quality building services. 28,000 solar panels, good insulation, high-performance glazing and separate energy meters for each compartment make the building sustainable in every respect. Aannemingsbedrijf Wouters Schijndel, for its part, records all traffic movements and uses recyclable materials wherever possible. “We no longer work on projects rated below BREEAM ‘Very Good’,” says Franco Nooijen of Aannemingsbedrijf Wouters Schijndel. “We know our part.”
A busy construction site
Given the scale of the project and the high construction speed required, the site was soon bustling with workers. “There were already around 80 to 100 people working on the foundations,” says Van Doorn. “Four piling rigs were on site, while demolition was still under way. Coordinating all of this is a logistical challenge.” Dividing the building into eight compartments helps.
Organisation and coordination
Despite the project’s immense scale, work is progressing well. Nooijen says: “The mild, wet winter has not been ideal for us, but we can manage. We are also holding many discussions with the client. Many decisions still need to be made about building services and fit-out. The installation work also needs to be coordinated. The scale and complexity of today’s ‘intralogistics’ are considerable. Users do not want to leave a single cm2 unused. Building services, fire safety and escape routes: everything has to be right. Fortunately, we have a good working relationship with the project developer. One eighth of the warehouse is being fitted out as a fully automated warehouse.”
The first three compartments are now standing. According to the schedule, the entire superstructure will be complete before the summer building holiday, and the DC will be wind- and watertight.