AFAS Experience Center | Piecing together elements made in-house

The AFAS Experience Center project calls for a specialist façade contractor capable of handling much of the work in-house. “BIM engineering, production, delivery and installation of the façade and supporting structure are our speciality,” says Jan Couwenberg, Head of Estimating and Sales at Leebo Intelligente Bouwsystemen. “Some of the 20,000 opaque façade elements, 13,000 of which are unique, require both volume production and bespoke solutions that few companies can deliver in-house.”
With the exception of the theatre dome, the façades of the various buildings at the AFAS Experience Center are clad in LeeBond, a ‘sleek, stable and lightweight’ aluminium composite skin (a thermoplastic polyethylene core with a 0.5 mm-thick layer of aluminium on each side) that offers considerable design freedom. The elements are CNC-milled in-house and combined with the LeeFrame steel subframe, which, like LeeBond, was developed in-house. Couwenberg explains: “LeeFrame is an inner leaf that allows for large spans and, like the façade cladding, is made up mainly of bespoke frames for this project. No fewer than 900 of the 1,150 LeeFrames are unique.”
Delivery and installation in a single day
Engineering based on the latest BIM updates and installation using the company’s own cranes enable a complete, project-specific delivery package, says Couwenberg. “With various state-of-the-art cranes and telehandlers, we can tackle any job, working in-house across the three construction phases for the office, theatre and central section.” Nothing can be stored on site, so just-in-time delivery has been carefully organised. “We deliver to order from our own production facility in Nieuwkuijk. The right elements are ready there, and anything delivered is installed the same day.” The variety of elements has already been mentioned, but to put it into perspective: the largest series of identical elements comprises 23 units, out of a total of 20,000. “So we have to be flexible, but the installation team remains manageable in size: between six and 18 people.”

One of the three construction phases covers the office building on the entrance side.
Ensuring quality
The Brabant-based façade contractor began installation this spring and hopes to finish in Leusden before the end of the year. “Why is a complete in-house delivery package so important? To give one example: the qv value (airtightness of the façade; ed.) is crucial here. The blower-door test is carried out at the exceptionally high pressure of 750 Pascal. When you engage with clients, as we have done here, as early as possible and keep as much as possible in your own hands, the required technical quality is well assured. It is a performance-based collaborative process. However, projects of this scale and with this degree of uniqueness are rare; few companies are equipped to supply the opaque façade sections for the AFAS Experience Center.”
Vraag over dit verhaal? Ask your question
Wie aan AFAS Experience Center werkte
- coördinerend constructeur
Lucassen bouwconstructiesMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build - ontwikkelende bouwerDura Vermeer Bouw HengeloMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
- uitwerkend architectLKSVDD-architectenMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
- designSteef van der VeldtMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
- architectenbureauJust ArchitectsMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
- hoofdconstructeurPieters BouwtechniekMentioned in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
- gevelbouwerLeebo Intelligente BouwsystemenIn dit verhaal
- liftenproducentKONEMentioned in AFAS Experience Center | Tailor-made lifts for the best ‘People Flow Experience’
- opdrachtgeverAFASMentioned in AFAS Experience Center | Tailor-made lifts for the best ‘People Flow Experience’
- staalconstructieBuiting StaalbouwMentioned in AFAS Experience Center, Leusden | Carefully monitored bespoke design
- systemsionairMentioned in AFAS Experience Center, Leusden | Air quality optimised to support ‘human capital’
- installateurHOMIJMentioned in AFAS Experience Center, Leusden | Air quality optimised to support ‘human capital’
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectAFAS Experience Center
- SubjectFaçades, roofs & roof gardens
- CompanyLeebo Intelligente Bouwsystemen