AFAS Experience Center, Leusden | Continuous process innovation in the service of results

AFAS Experience Center, Leusden | Continuous process innovation in the service of results

Construction of the AFAS Experience Center in Leusden is reaching a production peak in recent months, with 330 people on site. An integrated construction team comprising the Dura Vermeer/HOMIJ joint venture and AFAS is responsible for day-to-day planning, ongoing development during construction and quality control in the run-up to handover. “We leave nothing unattended when it comes up,” say AFAS construction project manager Wim Mars and Bas Beld, project manager for building contractor Dura Vermeer Bouw Hengelo.

Hogekwartier veld 2

Groundworks for the large water feature.

The AFAS Experience Center was designed in-house with a team of consultants, on a 4.5-hectare site directly opposite the existing office on Philipsstaat in Leusden. The new build comprises a group of interconnected buildings set in a rolling landscape with a water feature. These include an office section with a curved tension arch structure on the front elevation and a welcoming entrance, a dome-shaped theatre, and a restaurant with a vaulted roof and daylight features expressed through large overhangs and rooflights. “AFAS is committed to socially responsible commissioning, during the design phase, market consultation and the construction work that began in 2017,” says Mars. “Our collaboration with consultants and contractors is dynamic. We draw on as much innovative expertise from the market as possible to achieve the desired results.”

AFAS Experience Center, with the office section on the left and the theatre dome on the right.

Design sizing

The design of the AFAS Experience Center presents many challenges. With regard to ground conditions, review processes continue through to the landscaping, which has just got under way. For example, what effect will 1,200 cubic metres of soil used to shape the grounds have on the completed structures? The distinctive design language of the AFAS Experience Center calls for bespoke solutions when sizing the fit-out, from raised access floors to kitchenettes. “Nothing in the design is standard, driving continuous innovation. The façade finish is executed to millimetre precision, details and connections require close attention, and a theatre fit-out involves specialist materials and techniques that you have to pioneer together.” The right sustainability measures were still being selected during construction, including solar panels wherever possible and storage for the solar energy generated on site. “All flat and pitched roofs are now being fitted with ultra-lightweight polyester solar panels; the restaurant’s glass roof also incorporates integrated solar cells. The other roofs are covered with moss and sedum.”

de-constructieve-werkzaamheden-zijn-in-de-afrondende-faseent_i-kopieren

Structural work is nearing completion.

One site office

These are just a few examples, says Mars. Coordination takes place at a high level, resulting in solutions with broad support. “We work collaboratively and with a good balance alongside market parties such as consultants, contractors and suppliers. Communication and trust are essential. We leave nothing unattended when it comes up, otherwise it will be too late. We work together from a single site office, particularly on process matters. We also work together as a construction team on the reviews, including those carried out by the municipality. Inspections take place at the right time, all in the service of the end result.” This also benefits the contractors working under contract, says Beld. “For example, we saw an opportunity to improve the structure through a design change. We wanted to take a solution supported by the consultants and client into the review stages, and we succeeded. The project also uses as much prefabrication and plug-and-play installation as possible to ensure reliable logistics.”

Moving in

In mid-February, work is still under way across the campus on all fronts, from completing the structures to landscaping. The façades are almost finished, as is the perfectly round theatre dome, a real eye-catcher. Beld says: “With around 330 people on site every day, we are at the peak of construction output.” Integrating processes leads to better buildings, says Mars, but can also create bottlenecks. “You can have everything perfectly on track, but if delivery of the LED lighting is delayed by coronavirus, you are dealing with force majeure. Every now and then you need to take a break together, such as at a New Year’s gathering with presentations and dinner.” Beld adds: “It is good to celebrate results along the way too, for the benefit of the team.” The master construction schedule runs through to the summer. By then, the AFAS Experience Center will be more or less complete. Moving in begins after 1 September, ahead of the building opening on 1 January 2021. “In the final phase, we are working with the same parties as much as possible. Only the loose furniture is supplied directly by the client. And we have found a good tenant for the existing building, who will take over the current fit-out,” Mars concludes.    

Vraag over dit verhaal? Ask your question

Wie aan AFAS Experience Center werkte

  1. coördinerend constructeurLucassen bouwconstructiesGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  2. ontwikkelende bouwerDura Vermeer Bouw HengeloGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  3. uitwerkend architectLKSVDD-architectenGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  4. designSteef van der VeldtGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  5. architectenbureauJust ArchitectsGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  6. hoofdconstructeurPieters BouwtechniekGenoemd in Striking, challenging and complex: Dura Vermeer reaches highest point of AFAS new build
  7. gevelbouwerLeebo Intelligente BouwsystemenGenoemd in AFAS Experience Center | Piecing together elements made in-house
  8. liftenproducentKONEGenoemd in AFAS Experience Center | Tailor-made lifts for the best ‘People Flow Experience’
  9. opdrachtgeverAFAS SoftwareGenoemd in AFAS Experience Center | Leusden
  10. theaterkoepelOctatubeGenoemd in AFAS Experience Center | Leusden
  11. EPS-isolatieplatenKingspan UnidekGenoemd in Multifunctional roofs for the AFAS Experience Center
  12. rooferZND NEDICOMGenoemd in Multifunctional roofs for the AFAS Experience Center
  13. staalconstructieBuiting StaalbouwGenoemd in AFAS Experience Center, Leusden | Carefully monitored bespoke design

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectAFAS Experience Center
  • SubjectConstruction projects