EMA | Collaboration key to rapid delivery of substructure

Speed and collaboration were central to Augustinus BV’s work on the new European Medicines Agency (EMA) building. As a partner in the EMA construction consortium, Augustinus BV completed the entire substructure in just five months.
The substructure comprises the lower part of the building, up to ground-floor level. It contains a 3-metre-deep water cellar, a transformer pit and the core foundation block. The foundation block lies just below ground level and is a single solid mass measuring 800 square metres in area and 2.5 metres thick. Augustinus BV used around 4,200 cubic metres of concrete and approximately 850 tonnes of steel for the substructure as a whole.
Short construction period
Dura Vermeer, which later formed a construction consortium with Heijmans, approached Augustinus BV at an early stage to partner on the EMA building’s substructure. The specialist in foundations and basements, among other things, had previously worked with Dura Vermeer and demonstrated its expertise. “What makes this project unique is the very short construction period,” says Niek Augustinus, co-director of Augustinus BV. “Everyone involved is aware of this and is acting accordingly. The way the construction consortium embarked on this process with the subcontractors is unique. For example, we had already started work before the price was finalised. That shows the trust they placed in us and their confidence in our capabilities.”
Technical optimisations
Augustinus BV was closely involved in developing the concept drawings for the substructure. This took place during scrum sessions with the construction consortium and the structural engineer. These interdisciplinary sessions focused on ways to speed up the construction process. Most of the optimisations involved technical adjustments, such as the shape of the foundation block and how to accommodate changes in level. Keeping the detailing as simple as possible helped save time during construction.

Five months of construction
Construction of the substructure began at the end of May 2018. Site manager Hendrik-Jan Broekman was on site every day on behalf of Augustinus BV to supervise the work and respond quickly to ad hoc changes. He says: “We had until the end of October to complete the entire substructure. We met the first deadline before the summer building break. The core foundation block had to be ready by then, as the climbing formwork for the core was due to start rising in mid-August. On 31 October, we poured the final concrete, as planned.”
Perfectly executed
“From a technical point of view, constructing this substructure was a major project, involving the placement of a large volume of concrete and steel in a very short time,” Broekman reflects. “We have everything we need for that, in terms of knowledge and capacity, as well as equipment and materials. That includes formwork, reinforcement, and the necessary cranes and pumps.” Augustinus adds: “Despite the time pressure, the work went perfectly. The trust we were given, along with the close collaboration with the construction consortium and other parties, was fundamental to its success.”