Enexis Netbeheer and Van Wijnen launch large-scale rollout of prefabricated meter cupboards

Enexis Netbeheer can now install meter cupboards at the start of the construction process on new-build projects. This improves safety on site and ensures that more homes are completed on schedule. From this spring, Enexis Netbeheer will be ready to offer this concept to construction companies. It is being used for the first time at the Willemsbuiten site in Tilburg, where 98 of these meter cupboards are currently being installed. Van Wijnen, the contractor for this project, helped initiate and develop the idea of the prefabricated meter cupboard.
The idea is simple: install the meter cupboard as soon as the ground-floor slab has been laid. This makes the site much less busy. There are no painters, bricklayers or tilers, nor any scaffolding or building materials to make the connection more difficult. The contents of the meter cupboard remain unchanged. With a sturdy, watertight and weatherproof enclosure that can be locked, the meter cupboard is safe and protected from external conditions. The contractor installs and assembles the meter cupboards, after which Enexis Netbeheer connects them on site.
Safer working
This brings several benefits for both Enexis Netbeheer and the builder. “We’re very pleased to be able to offer this option from now on,” says Lotte Breunesse, Consumer Manager at Enexis Netbeheer and, in that capacity, a board member of Mijnaansluiting.nl. “Previously, we would first arrange a temporary construction connection for the site. Shortly before completion, we would return to arrange the permanent connection. That is no longer necessary with a prefabricated meter cupboard. The contractor can use it during construction, and the residents can use it afterwards. So we don’t have to come back.”
This has made work on site safer, says Bart Kierkels, project manager at Van Wijnen: “Previously, we had a large number of cables running across the site. That number has been greatly reduced because each home already has its own electricity connection.” Fewer cables mean less risk of tripping.
Easier planning
It is also easier for the contractor to schedule Enexis Netbeheer’s work. When a meter cupboard is connected towards the end of the construction process, the schedule also depends on the other parties that need to work on site first. The prefabricated meter cupboard avoids this, allowing more homes to be completed on schedule. “We can now manage the schedule and safety effectively. We can plan the connection to each home down to the day,” says Bart Kierkels.
Successful pilots
Successful pilots have been carried out in Assen and Groningen (>200 homes). They provided the knowledge needed to make the prefabricated meter cupboard the standard. Mijnaansluiting.nl facilitates this process, with Enexis Netbeheer closely involved in managing risks and agreeing on safe working practices. The prefabricated meter cupboards used in Tilburg were made by De Verbinding BV, a social enterprise employing deaf carpenters.