General

Extended A16 set to improve regional connectivity and quality of life

Extended A16 set to improve regional connectivity and quality of life

After a long lead-up and a first year of tangible work, the new section of the A16 above Rotterdam is beginning to take shape here and there. The route is already clearly visible from the air, preparations are under way for the first structures, and the first million cubic metres of sand have been delivered. According to the schedule, the new, 11-kilometre stretch of motorway will open to traffic at the end of 2024.

The new motorway connects the A13 by the airport to the A16 at Terbregseplein. This will separate the north-south and east-west routes at this junction. The intended result is less congestion on the A20 between Kleinpolderplein and Terbregseplein, less rat-running on local roads in the surrounding neighbourhoods, and better accessibility for the rapidly growing municipality of Lansingerland. The project is being delivered on behalf of Rijkswaterstaat by De Groene Boog, a consortium of Besix, Dura Vermeer, Van Oord, John Laing, Rebel and TBI (Mobilis, croonwolters&dros), operating under a Design, Build, Finance & Maintain contract with a 20-year maintenance obligation.

Bat screens at the tunnel site where trees have been felled. (Image: Tjerk van Duinen)

Soft ground

From the site office on Vliegveldweg, Besix project manager Daniel van Dorsselaer has a good view of some of the many work packages. “This project involves some big numbers. On 20 May, we celebrated the delivery of the first of four million cubic metres of sand. The sand is being used as surcharge to consolidate the soft subsoil. This is necessary for the new motorway, but also for the temporary infrastructure used by construction traffic. We are not allowed to use the local road network beneath the site, and have no reason to do so. A stationary lorry costs money, so we mainly travel outside peak hours.”

Time savings

The vast quantity of sand comes from the Markermeer and the North Sea and is shipped to four unloading locations. From there, it is taken by lorry to the construction sites. Van Dorsselaer says: “This is carefully planned, with set times and adjustments if our monitoring shows that starting 15 minutes earlier would save time. Nitrogen restrictions and PFAS have caused a delay of almost a year; we are trying to make up for it with new, smart measures.”

A13-A16 junction. (Image: De Groene Boog)

Embankments

The first signs of the new motorway are already visible in several places. Preparations are in full swing for building the abutments of the flyover at Terbregseplein; at the covered section over President Rooseveltweg in Ommoord, the embankment and temporary construction bridge have been built; the first few hundred metres of sheet piling have been installed for the construction of the more than two-kilometre tunnel trough by Bergse Bos; and elsewhere, the main task is bringing in sand, a great deal of sand. Van Dorsselaer says: “We make the most of every job. Once a temporary structure or earth embankment is no longer needed, the sand is used elsewhere.”

Sustainable

As its name suggests, De Groene Boog owes much of its success in winning the tender to its extensive focus on sustainability and its responsibility towards the living environment and local residents. This involves more than building separate infrastructure for construction traffic and using smart traffic management. The entire road and tunnel will be energy-neutral through the use of solar panels and smart tunnel systems. Four-metre-high noise barriers will be installed. Temporary bat screens at the tunnel will help these animals find their way during construction, despite the trees having been removed, and piling will not take place during the breeding season. Van Dorsselaer says: “We are working under an EMVU tender, which stands for Economically Most Advantageous Execution. De Groene Boog has a fund to keep looking for improvements during construction. For example, the thousands of deliveries are made using HVO biodiesel. It costs more, but fits perfectly with De Groene Boog’s values.”

Daniel van Dorsselaer by the sheet piling for the tunnel trough: “Nitrogen restrictions and PFAS have caused a delay of almost a year; we are trying to make up for it with new, smart measures.” (Image: Tjerk van Duinen)

Availability

The consortium still faces a considerable number of challenges. Terbregseplein junction is a major project in its own right, as is the tunnel with its thousands of piles. Slip roads will connect to the N209 (Bleiswijk) and N471 (Berkel Rodenrijs), and this work must also be carried out with as little disruption to traffic as possible. The HSL and Randstadrail must be crossed in quick succession, while avoiding the HSL tunnel foundations, which means piles up to 60 metres deep are required. Connecting to the A13 is also a complex operation, with only a few weekend closures available. Van Dorsselaer concludes: “The finished project will be in place in a few years. Everything has to work very well. De Groene Boog is responsible for maintenance and availability for 20 years. If there is water on the road surface, subsidence occurs or other stoppages for which we are responsible, our availability payment will be reduced. That is an excellent incentive to deliver the work to the highest standard.”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.