Distribution centres

Magna Tyres, Waalwijk | A project with challenges

Magna Tyres, Waalwijk | A project with challenges

Magna Tyres Group is building a new distribution centre alongside the A59. The tyre specialist has opted for a centre that meets the highest quality standards and is designed to achieve BREEAM ‘Excellent’ certification. This presents some unique challenges.

Impressive figures, high quality standards and BREEAM ‘Excellent’

The new Magna Tyres Group distribution centre has a total floor area of 57,671 m², including the office. The centre has a loading bay on each side, with 48 docks in total. The office will be equipped with every amenity. Employees will be able to enjoy a luxury canteen, professional kitchen, fitness room and associated sanitary facilities. The contractor for the distribution centre is Willy Naessens Nederland, which has been involved in planning the construction from the outset.

Hybrid construction

“The original design called for a steel structure,” says Herman Wijgerse, project manager at Willy Naessens Nederland. “By switching to a concrete frame, we were able to eliminate two rows of columns and foundations. This gives Magna Tyres considerably more space. The steel roof decking and sandwich-panel cladding have been retained, making it a hybrid construction.”

De kozijnen worden gerenoveerd volgens een speciaal ontwikkeld kozijnenplan.

Switching from a steel structure to a concrete frame made it possible to eliminate two rows of columns and foundations.

Impressive figures

Willy Naessens first had to prepare the muddy site for construction. It used cement-bound soil stabilisation to prepare the ground for heavy machinery. Piling work could then begin. “This is the largest project we have undertaken in the Netherlands to date,” says Wijgerse. “That means some impressive figures. We drove more than 1,000 precast piles into the ground, with an average length of 10 m. The foundations and loading bays include around 300 pile caps and 500 m of foundation beams. The 17,000 floor piles were installed at a rate of 300 per day.”

Logistical challenge

The concrete structure for Hall A posed a challenge in terms of assembly and production. Wijgerse says: “The concrete elements were produced at our 15 factories in Belgium. It took 900 deliveries to bring them to the site over 60 days. That meant 15 loads per day.” Once the concrete frame had been erected, the façade cladding, steel roof decking, insulation and PVC roofing were installed at a rate of 5,000 m² per week.

BREEAM ‘Excellent’ challenges

Achieving BREEAM ‘Excellent’ certification is an ongoing challenge. Factors such as CO2 emissions, traffic movements, natural features, waste streams and energy consumption must be closely monitored and recorded. Bat boxes, an insect hotel, suitable planting and amphibian ramps must also be provided. And the site has to be kept tidy. Wijgerse says: “It’s a large project, but it has been well prepared. Everyone knows what is expected of them. Now we just have to keep the project running at pace. In that respect, one large project takes less effort than three small ones. So, as far as I’m concerned, a project can never be too large.” Magna Tyres is expected to start using the distribution centre in early November. The office is due for completion around March 2020.

A business enquiry for Willy Naessens Nederland? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectDistribution centres
  • CompanyWilly Naessens Nederland
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.