Prefab concrete frame system enables predictable construction
Text Jan-Kees VerschuurePhotography Bestcon

The entire prefabricated concrete frame of the Grote Beer apartment building is produced, delivered and assembled by Bestcon, with structural floor slabs provided by the Bestcon60 frame system. This enables highly predictable construction, says project manager Marc van Zeijl. “The floor slabs are ready for use as soon as they are installed, allowing other contractors to work efficiently below them.”
The prefabricated frame of the Grote Beer comprises 21 storeys and starts at the first-floor slab, which is cast in situ. Frame assembly begins in week 6 and continues until week 40. The total structural floor area is 17,000 m². The Bestcon60 high-rise frame system consists of solid, prestressed precast elements that allow for large spans. The floor slabs are supported by the walls, forming fully structural floors.
A third party applies the foam concrete topping in a subsequent ‘train’, incorporating all the building services. Van Zeijl says: “This topping is non-structural, so the logistics of assembling the frame, installing the service floors and the work of the building services installers do not interfere with one another. That way, everyone can focus on what they do best. This method makes frame construction highly predictable for all the trades working after assembly. We also have to contend with a very restricted construction site, with space for just two lorries. Because our impact on the site is minimal and we deliver everything just in time, we have managed to make this work well.”
Ramping up production
The balconies are cast onto the elements at the concrete plant. All elements are delivered just in time during the assembly period, in 560 lorry loads (7 to 10 per day), and installed immediately. Each day, 200 to 300 tonnes are hoisted into place, a major logistical operation for Bestcon. “Production of the precast elements is also just in time, with 13 million kilos of concrete in total. Although a storage hub is available near Rotterdam, we use it as little as possible,” Van Zeijl continues. “The building narrows towards the top, so we aim to reduce the time needed to complete a storey to 4 days, from one week. The building has been designed clearly and efficiently, and we do not expect any structural problems during assembly. Once a floor slab has been installed, the storey below is weather-tight, allowing other contractors to continue their work unhindered.”