Horizon College’s frame and façades come from the factory

Horizon College’s frame and façades come from the factory

By using two Leebo construction systems, contractor SMT was able to build the new Horizon College building in Purmerend using prefabricated components. “At the construction site, all they had to do was click the various components together.”

It took just three weeks in autumn 2018 to make the new Horizon College building in Purmerend, North Holland, wind- and watertight. According to Jan Couwenberg, head of estimating and procurement at Leebo, this was thanks to the company’s LeeFrame façade system. “The major advantage of this prefabricated system, with insulated cavity wall panels in a steel frame, is that it is easy to assemble on site. The various prefabricated components are made in our factory in Nieuwkuijk and simply need to be put together at the construction site. This means fewer skilled tradespeople are needed, and there was a shortage of them during the tender period.” In his view, using this system has a major influence on the construction team. “The system sets the direction, which meant we were able to contribute a great deal to the construction team. Since we have been working with it for more than fifteen years, the architect, in this case JHK, had plenty of scope to design the building.”

LeeBrick is a dry construction system.

Dry construction system

Once the LeeFrame structure had been made wind- and watertight, the LeeBrick façade system was also installed. It consists of brick façades that can be stacked in a variety of bonds without pointing. “This façade system is attached to the cavity wall panels of the LeeFrame system. Essentially, we have split the façade into two parts,” Couwenberg explains. “Another advantage of the LeeBrick system is that it is a dry construction system, which prevents white efflorescence from forming on the bricks.” A visit to ROC van Almelo, for which Leebo also used the LeeBrick system in 2004, convinced JHK and SMT to use it for this project. The new Horizon College building officially opened last September. That does not mean Leebo’s work is finished. “We will visit again next spring to see how the building has been affected by the changing seasons,” says Couwenberg.  

Question about this story? Ask your question

Who worked on it

Horizon College in Purmerend

  1. construction companySMT
  2. architectJHK

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectHorizon College
  • SubjectEducation
  • CompanySMT
  • CompanyJHK
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.