General

Theemsweg route, Rotterdam | Diverting a section of port railway

Theemsweg route, Rotterdam | Diverting a section of port railway

Contractors’ consortium SaVe is rapidly building the substructure for the Theemsweg route, due to be completed by the end of 2021: a clever diversion that will allow the Port of Rotterdam Authority to prevent future congestion on rail and waterways. A major feat of engineering.

Theemsweg route resolves bottleneck at Calandbrug

All modes of transport converge at high intensity in the Port of Rotterdam. When bottlenecks threaten to emerge, it is vital to anticipate them quickly and effectively. The Calandbrug near Rozenburg is one such bottleneck. This steel lift bridge, built in 1969, is part of the Betuweroute, the rail link between the western port area and the hinterland, and provides access to Brittanniëhaven for seagoing vessels. Compared with 2010, the number of daily bridge openings is expected to double by 2030, while the number of trains per day is set to at least double. To prevent this gridlock, a clever diversion has been devised so that rail traffic no longer crosses the shipping route: the Theemsweg route.

Bridge over the Rozenburgsesluis.

Connecting Together

The diversion consists entirely of a viaduct that starts just before the Calandbrug, where the new railway line turns right and crosses the Thomassentunnel’s sunken section via a bowstring bridge. At the Neckarweg, the viaduct crosses the line of wind screens, then continues for three kilometres along the Theemsweg after crossing the Rozenburgsesluis via a second bowstring bridge. It connects to the existing railway along the A15 at the Merseyweg. The substructure of the Theemsweg route is being built by contractors’ consortium SaVe, short for Samen Verbinden, or Connecting Together, which brings together BESIX, Dura Vermeer, Mobilis, Hollandia and Iemants (Iemants is the contracting party for Smulders). Work is progressing well: SaVe won the tender in November 2017, against four other bidders, construction began in September 2018, and the consortium will hand over the project to the railway systems contractors at the end of 2020. The first trains can run at the end of 2021.

Aerial view of part of the project area. (Photo: PortPictures/Danny Cornelissen)

4D

“That is certainly a fast pace,” says Dieter Behaeghel, SaVe project manager. “And despite the scale of the project, its technical challenges, neighbouring businesses wanting to operate 24/7, the different types of infrastructure involved and the array of underground pipes and cables, we are on track. Connecting together means working well together and paying attention to relationships. Not only with our partners, but also with the Port of Rotterdam Authority, all stakeholders and the project’s surroundings. Our aim is to start every task safely and with proper preparation. The entire project has been developed in BIM, but in 4D, combining 3D with scheduling. This allows us to identify potential clashes in advance, for example involving crane positions, the transport of large elements and construction pits.”

Het water stroomt over het profiel naar een smal sleufje met daaronder enkel een compact puthuis.

Dieter Behaeghel: “Good relationships with all stakeholders are essential.”

Subprojects

The Theemsweg route is four kilometres long in total and has been divided into subprojects, each with its own contractors. Behaeghel: “The viaduct along the Theemsweg, for example, is a single workstream. Foundations are being built in sequence, pile caps and columns cast, precast support beams laid and 30-metre-long girders installed. And that process is repeated around 70 times. The steel bridges are separate projects, carried out in parallel.”

Zodra je merkt dat het douchewater minder snel wegloopt, verwijder je het doucherooster zonder gereedschap met de slimme ‘tip&flip’ functie.

Bridge under construction over the Thomassentunnel.

Hollandia and Iemants are building the bridges. Last summer, they floated their bridge sections into place and began assembling them at the pre-assembly sites. The bridges look identical, but the one over the Thomassentunnel is just over 270 metres long, including its approach sections, while the bridge over the lock is more than 170 metres long. It is heavier and wider because the railway curves there. The steel alone weighs 4,200 and 4,300 tonnes respectively. Once in position, each bridge will receive a heavily reinforced concrete deck, almost doubling its weight.

Cast columns stand ready along the Theemsweg for the installation of support beams

Four kilometres of construction site

In addition to these high-profile subprojects, there are many smaller works that have been completed or are still to come. The Port of Rotterdam Authority had already relocated the main railway line and cycle path on the Theemsweg and raised a pipe bridge from seven to 17 metres. SaVe itself moved the Theemsweg north in stages to make room for the new railway viaduct. In 2018, three large sections of the distinctive wind screen at the Neckarweg were demolished to allow the railway viaduct to pass through. On the other side of the road, the Port of Rotterdam Authority had built a row of narrower new sections in advance. Near the Neckarhaven, the viaduct runs partly across Vopak’s site, so the company will have to shut down operations for a weekend when the time comes. Behaeghel: “That really shows how important it is to stay in contact with stakeholders. Your construction site is four kilometres long, partly built-up and partly in use. You can only succeed if you sort that out properly in advance.

Vraag over dit verhaal? Ask your question

Wie eraan werkte

Theemswegtracé in Rotterdam

  1. aannemersconsortiumSaVe: Samen Verbinden
  2. bruggenbouwersHollandia
  3. bruggenbouwersIemants

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectTheemswegtracé
  • OnderwerpGeneral
  • CompanySaVe – Samen Verbinden
  • CompanyHollandia
  • CompanyIemants
Deel dit artikel

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.