Twintec Nederland completes DC Distripark project in Dordrecht

Working with Hercuton, we delivered the floors for the new Crocs distribution centre. The floor was designed according to Twintec’s Design, Build and Guarantee principle.
Our in-house engineers selected the Twintec Ultimate floor as the solution, supported on HSP piles to suit the ground conditions in the region. Our own Twintec team delivered the high level of flatness required by DIN 15185, comfortably meeting the standard.

We installed 42,000 m2 of Twintec Ultimate in 23 days, using our in-house-produced Laserscreed and Toppingspreader in combination with our own skilled workforce. In short, Twintec delivered a complete solution that we can be proud of.
Have a business enquiry for Twintec? Get in touch
Wie aan DC Distripark werkte
- Mechanical and electrical installationsVink Installatie GroepMentioned in ‘These measures will create an attractive, sustainable building’
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDC Distripark
- SubjectDistribution centres
- CompanyTwintec