De bouwkuip.
De bouwkuip.

Commissioned by HSB Bouw, HeSto VOF, a joint venture between Gebr. van ’t Hek and Roel van der Stoel B.V., carried out the foundation and earthworks for Brisk’s sunken car park. “A challenging construction pit, requiring close coordination between the construction teams,” says Marco van der Hulst, site manager at Roel van der Stoel B.V.

The HeSto formula integrates operations in the complex environment of the construction site. Gebr. van ’t Hek (foundation engineering) and Roel van der Stoel B.V. (earthworks) work as a permanent team to manage logistical challenges during construction: delivering a complete construction pit through an integrated project approach that takes the burden off the client. “During the project’s preparatory phase, we advised HSB Bouw and actively contributed ideas on the construction phase. Throughout the project, we worked closely together, based on strong mutual trust.”

Construction and discoveries

For the Brisk construction pit, Roel van der Stoel B.V. was responsible for setting up the site, diversion routes, the baseline survey of the infrastructure, temporary parking facilities and the (dry) excavation of the pit. During excavation, the company found that the soil profile in practice differed from expectations. This caused problems involving the first aquifer, as the confining layer had been perforated in several locations. To prevent damage to the dewatering system, two trailers carrying Mikolit (high-quality clay granules) were brought in to carry out repairs.

Fast and efficient

Van der Hulst: “During excavation, we went down to a depth of 8.45 metres below NAP, removing 32,000 cubic metres of soil, which was environmentally tested and approved for reuse elsewhere.” Groundwater pressure is high in the built-up area of Amsterdam Zuidoost, and dewatering a construction pit of this length is challenging, so the foundations had to be installed quickly and efficiently. “What you are effectively doing with a construction pit like this is creating a polder, and it has been applied successfully here over the past year,” concludes Van der Hulst.

Question about this story? Ask your question

Wie aan Brisk werkte

  1. prefabricated reinforcement meshWadroMentioned in Optimised prefabricated reinforcement for concrete structures
  2. clientSynchroonMentioned in Careful construction for a high-quality urban transformation
  3. main contractorHSB BouwMentioned in Careful construction for a high-quality urban transformation
  4. architectArons en Gelauff ArchitectenMentioned in Careful construction for a high-quality urban transformation
  5. Foundation and groundworksHeSto VOFIn this story
  6. foundation engineeringGebr. van ’t HekIn this story
  7. groundworksRoel van der Stoel B.V.In this story
  8. project initiation and developmentXior Student Housing (Xior BrinkToren NV)Mentioned in 880 precast concrete elements for the Netherlands’ first energy-positive residential tower
  9. developmentDubbeLL buurtontwikkelaarsMentioned in 880 precast concrete elements for the Netherlands’ first energy-positive residential tower
  10. developmentMunicipal propertyMentioned in 880 precast concrete elements for the Netherlands’ first energy-positive residential tower
  11. main contractorCordeel Amsterdam VOFMentioned in 880 precast concrete elements for the Netherlands’ first energy-positive residential tower
  12. precast concrete facade elementsLoveld N.V.Mentioned in 880 precast concrete elements for the Netherlands’ first energy-positive residential tower
  13. Glazed façades and glazingVorsselmansMentioned in BrinkToren: a striking finishing touch for Amsterdam-Overhoeks
  14. EnergyFacade solar panelsSaint GobainMentioned in BrinkToren: a striking finishing touch for Amsterdam-Overhoeks
  15. installerHomijMentioned in BrinkToren: a striking finishing touch for Amsterdam-Overhoeks

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBrisk
  • SubjectModular construction
  • CompanyHeSto VOF
  • CompanyGebr. van ’t Hek
  • CompanyRoel van der Stoel B.V.
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.