Complex groundworks beneath the A10 and on the Zuidas

Text Roel van GilsImage Bonneveld, Marcel Steinbach

Op dit project moest Bonneveld tot wel 900 kuub per uur verzetten met vijf rupskranen die dag en nacht draaiden.
Op dit project moest Bonneveld tot wel 900 kuub per uur verzetten met vijf rupskranen die dag en nacht draaiden.

Careful planning and close collaboration

Normally, a closure of this kind involves digging a hole, sliding a tunnel into place and then backfilling it. This time, the situation was more complex: the A10 works were split into two phases, east and west, with additional activities including soil improvement, the construction of transition structures, the installation of EPS and the laying and levelling of the sub-base for the asphalt. Stefan Albers, technical director at Bonneveld, explains: “Soil improvement proved necessary because there was contamination and ground with insufficient bearing capacity beneath the fill layer, from NAP level downwards,” he says. Working under remediation conditions and adjusting an already tight schedule made the project particularly challenging. “Whatever you remove, you have to put back,” says site manager Timo van Wegen. “We moved more cubic metres than anticipated, worked closer to the groundwater level and installed drainage. Although the client was responsible for the dewatering, we installed the drainage and had to ensure the ground was stable again.”

Bonneveld moved more cubic metres than anticipated, worked closer to the groundwater level and installed drainage.

Familiar faces

Work resumed immediately after the A10 reopened. In the central area, tracks were removed to make room for piles and abutments. The contractor was then able to slide the deck structures into place. “It really was like working on a postage stamp,” says Van Wegen. “There was no room at all for delays or surprises, so communication was crucial to meeting the schedule.” Albers adds: “It makes a huge difference that we always work with the same subcontractors. Everyone knows one another and knows what is expected of them. The points of contact on the client’s side and in our project team have also remained the same since the start of the project, which keeps communication lines short.”

Large-scale earthworks

Alongside the ‘agreed’ work during the closure, Bonneveld also carried out additional work at Amsterdam Zuid station, under the direction of the construction consortium. Meanwhile, construction of the Brittenpassage continued, involving the excavation of more than 30,000 cubic metres of soil beneath the motorway. Asked about the project’s biggest challenge, the answer is unanimous: “The location. The Zuidas is a busy hub with limited space and high visibility. You are right in the middle of the city, with busy access routes, BLVC plans and passengers continuing to use the station,” says Albers. “That calls for precision and flexibility.”

Bonneveld has the people and machinery needed to make complex projects like this a success. “Whether it is beneath a railway or a motorway, with or without contamination, this is exactly where our expertise lies,” Albers stresses. “On this project, we had to move up to 900 cubic metres per hour, using five crawler excavators running day and night. Thanks to our extensive and motivated workforce, we can now deliver that with ease.” Another deck slide is scheduled for early next year, following the same principle. For Bonneveld, that means careful planning, close collaboration and moving forward at full speed once again. 

A business enquiry for Bonneveld? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectModular construction
  • CompanyBonneveld
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.