‘Floating’ platform canopies for OVT Zuid
Text Roel van GilsImage Sorba

The renewal and expansion of the station area at Amsterdam Zuid is becoming increasingly visible. Sorba has worked on the ceiling and roof cladding for the striking platform canopies, which appear to float above the platforms thanks to the high-quality finish of the special aluminium composite panels.
The new platform canopies are replacing the existing structures above the tracks. “In close collaboration with steel construction contractor Buiting Staalbouw, we are providing the aluminium composite cladding around the canopies, including the underside”, says Ken Rouwenhorst, project engineer at Sorba. “A metallic colour with a Lumiflon coating was chosen, carefully selected by the architect. All joints and substructures are finished in black, creating a clean, uniform appearance and making the canopies seem to float.”

Made to measure
The project has been divided into phases: each platform canopy is prepared separately at the steel contractor’s premises, transported to the site in sections and lifted into place over a single weekend. Sorba is also carrying out much of the preparatory work in-house. “At our facility in Winterswijk, the 6 mm Alpolic aluminium composite panels are made to measure and assembled. We then take the material to Buiting Staalbouw for further assembly. That applies only to the cladding that does not obstruct transport”, Rouwenhorst explains. “Once the framework has been erected at the station, we carry out the remaining finishing work.”
8,500 m² of cladding
For the first phase, Sorba is supplying a total of 8,500 m² of cladding, divided across four platforms with canopies measuring 140 metres long and up to 14 metres wide. “One of the biggest challenges lay in the design. A separate nose profile was originally planned, but because of the aesthetics and the risk of colour differences, we proposed an alternative: a solution made entirely from a single material. The 40 mm curve in the panels also required a bespoke solution: a relatively small radius that is not standard practice when processing composite material. But it is precisely this that gives the canopies their desired slender, almost floating appearance.”
A calling card
The first canopy has now been successfully installed and serves as a calling card for the next phases. Work will continue until mid-2026, when the final canopy is also due to be completed. Sorba is a familiar presence at railway stations across the Netherlands. “Drawing on our experience from previous public transport projects, including Breda, Arnhem, Den Haag and Amsterdam, as well as platform canopies at Utrecht CS, Arnhem CS and Amsterdam RAI, among others, we bring specialist expertise in construction work in railway environments.”
Question about this story? Ask your question
Who worked on OVT Zuid
- aluminium composite claddingSorbaIn this story
- steelwork contractorBuiting StaalbouwIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectOVT Zuid
- SubjectModular construction
- CompanySorba
- CompanyBuiting Staalbouw