Modular construction

Fast construction at Jacob Geelbuurt thanks to tunnel formwork

Text Reina LantersImage Casco Bouw Nederland

Een eerste indruk van de nieuwe Jacob Geelbuurt.
Een eerste indruk van de nieuwe Jacob Geelbuurt.

Jacob Geelbuurt in Amsterdam is undergoing a major renewal. Various parties are working closely together to deliver, among other things, 262 rental homes in the first phase. Contractor De Nijs was looking for a tunnel-formwork specialist for the project. It found the right partner in Casco Bouw Nederland, based in Staphorst. “In terms of tunnel formwork, the project is a perfect fit for us,” says director Jan Hokse.

With 262 homes, Jacob Geelbuurt in Amsterdam is a sizeable neighbourhood. That makes it an ideal project for tunnel formwork, says Hokse. Main contractor De Nijs had no experience with this type of structural work and was looking for a partner with the expertise to guide the process. Casco Bouw Nederland proved to be the right choice. Hokse: “We hit it off straight away in our first meeting. The down-to-earth nature of people from North Holland is a good match for that of people from Staphorst.” Casco Bouw Nederland ultimately handled the entire tunnel-formwork process, including supplying the tunnel formwork, ready-mix concrete and reinforcement, as well as placing the reinforcement.

Easy to manage

Tunnel formwork is a method of structural construction in which the concrete shell of a home is cast floor by floor. It is a highly efficient way of working, particularly when all the homes are roughly the same size. Casco Bouw Nederland began the tunnel-formwork work in July 2022. By April 2023, all 302 bays were complete and the tunnel forms had been removed from site. The project ran smoothly. “We maintained a consistent output of 2 bays a day. This makes the process easy for the client to keep track of,” says Hokse. In addition to the tunnel-formwork work, Casco Bouw Nederland also built the stairwells and lift cores.

A few challenges

The design presented two challenges for the specialist tunnel-formwork contractor. These were resolved in collaboration with formwork supplier Hendriks Stalen Bekistingen. The tunnel forms were fitted with sluice winches, allowing bays of different widths to be cast using the tunnel-formwork system. The ground floor also had a non-standard storey height. “By using tall kicker forms and support structures, we were able to use tunnel formwork throughout,” says Hokse. “That meant we could still help maintain the fast pace of construction.” And just as importantly, the atmosphere on site was always good. Hokse: “De Nijs was looking for a down-to-earth, transparent approach that puts people first. That’s exactly what we’re about. We enjoyed doing the work!”  

Question about this story? Ask your question

Wie aan Jacob Geelbuurt werkte

  1. Construction companyDe NijsIn this story
  2. tunnel contractorCasco Bouw NederlandIn this story
  3. formwork supplierHendriks Stalen BekistingenIn this story
  4. building services adviceHiensch EngineeringMentioned in Green living in central Amsterdam
  5. building servicesStebomaMentioned in Green living in central Amsterdam
  6. ClientDe AlliantieMentioned in Green living in central Amsterdam
  7. architectGeurst & Schulze ArchitectenMentioned in Green living in central Amsterdam
  8. structural engineerVericonMentioned in Green living in central Amsterdam
  9. building services adviceHalmos adviseursMentioned in Green living in central Amsterdam
  10. building servicesBlom ElektrotechniekMentioned in Green living in central Amsterdam

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectJacob Geelbuurt
  • SubjectModular construction
  • CompanyDe Nijs
  • CompanyCasco Bouw Nederland
  • CompanyHendriks Stalen Bekistingen
Share this article