Warm cast-in-place concrete is making a comeback

Text Els HekkenbergImage Verboom Techniek en Waal

Warme gietbouw wint weer aan populariteit.
Warme gietbouw wint weer aan populariteit.

Building more sustainably with gas and less cement

De Limes in Oegstgeest is being built using warm cast-in-place concrete. For years, the cold method was standard, but stricter environmental requirements and shortages of raw materials are driving a shift back, says Xander Schuite, director of Verboom Techniek. The company supplies the heating systems and measures when the concrete is strong enough to strike the formwork.

Cold cast-in-place concrete uses fast-setting cement with a high proportion of Portland clinker, which has a large carbon footprint. With warm cast-in-place concrete, gas burners heat the concrete from the outside, allowing slower-setting cement to be used. A Stufib/Stutech study found that warm cast-in-place concrete is also more environmentally friendly than the cold method, even when gas consumption is taken into account.

A maturity meter is used to determine the right time to strike the formwork.

“For a long time, many contractors preferred cold cast-in-place concrete as a simple solution,” says Schuite. “And cement suppliers kept the mixes competitively priced. If you can achieve the required strength within fourteen hours without heating, it’s the obvious choice.” But the raw materials for cold mixes are becoming scarcer and more expensive. At the same time, clients and municipalities are pushing contractors to consider emissions. “Major companies such as Waal and other leading cast-in-place contractors are now taking a serious look at warm cast-in-place concrete again.”

Monitoring and control

Three tunnel formwork systems were installed at De Limes. Verboom fitted them with a heating system and sensor positions. The MCR-21 maturity meter continuously measures the temperature and weighted maturity of the concrete. Once the required strength is reached, the system switches off automatically. Schuite says: “This means you use gas as efficiently as possible, while also having documented evidence that you struck the formwork at the right time.”

The data is available online. If readings deviate, Verboom can adjust the system or, in consultation with the concrete supplier, modify the mix. “We act as independent advisers on the curing process for most contractors. It’s a great collaboration with site managers, structural engineers and concrete suppliers.”

Gas tank on site

Installing a propane tank on a construction site requires coordination with the environmental service. National regulations govern distances and safety, and municipalities may impose additional requirements. Schuite says: “So far, we’ve always been able to make it work, but sites in urban areas are becoming more constrained and the rules are getting stricter.” Since 2020, Verboom has worked with gas supplier Robogas to ensure safety and compliance with regulations.

The work at De Limes went smoothly. Schuite says: “Waal is a very good partner in that respect. There was plenty of room on site and the system ran smoothly.” Once the final part of the structural frame has been poured, the tank and burners are removed and construction can continue.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectModular construction
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.