Work has begun in Haarlem on the first phase of the HIGH5 new-build project, part of the Schalkwijk Centrum area development. Bonneveld is responsible for setting up the site and excavating the building pit. Through careful phasing, the specialist earthworks contractor in the commercial and infrastructure sectors makes ‘work work’ and keeps the movement of materials to a minimum.

HIGH5 is a development by HBB Groep and Hoorne Vastgoed, which are building five structures in phases, providing a total of 569 apartments. “We have a longstanding relationship with HBB and are a regular earthworks partner. We laid the foundations for Hotel de Koepel in Haarlem at an earlier stage, for example,” says Anco van der Heiden, co-owner of Bonneveld. “For HIGH5, we have been commissioned to carry out the earthworks for three of the five buildings. We have already set up the site and created access to it by constructing a large temporary bridge over the water. Our scope also includes dewatering, both phreatic and confined groundwater. All in all, it is a substantial project for us.”

To improve access to the site, Bonneveld built a temporary bridge between Briandlaan and Costa Del Sol.

Temporary bridge

A watercourse runs around the site. “To improve access, we built a temporary bridge between Briandlaan and Costa Del Sol. In early October 2024, we installed a piled structure consisting of three steel culvert pipes, each 21 metres long and 142 centimetres in diameter, supported on timber piles,” explains Van der Heiden. “We then laid the surface, using 74 industrial panels. The bridge itself is a generous 10 metres wide and is intended for construction traffic, emergency services and visitors to the gym in the temporary accommodation on the site. Construction traffic is, of course, separated from other traffic by concrete barriers.”

Extensive site set-up

To create a level, dust-free site, Bonneveld levelled the surrounding area and covered it with more than a thousand industrial panels. “Sterk BV installed a temporary sheet-pile wall on the Haarlemmervaart side, 5 metres from the water’s edge, and backfilled it with sand,” says Peter Koelewijn, work planner at Bonneveld. “This was necessary because the residential towers will eventually have façades standing in the water. We also installed a Berlin wall so that, after excavation, the contractor can safely construct the foundations.”

Careful phasing

The building pit for the first three residential towers covers just under 6,000 m2. Van der Heiden says: “Our approach is to keep as much soil as possible on site. Although soil is moved around the site, it is reused later. This enables us, for example, to install the working layer as economically as possible. In the first phase, we excavate between the more than 700 piles using our specialist equipment, which is fitted with GPS.” Bonneveld will eventually have to remove 7,500 m3 of soil, but twice that amount will be excavated. “So it all stays on the project. It is a matter of careful planning and phasing.” Bonneveld began excavating the building pit at the end of January 2025.

A business enquiry for Bonneveld? Get in touch

Who worked on HIGH5

  1. groundworksBonneveldIn this story
  2. developmentHBB GroepIn this story
  3. developmentHoorne VastgoedIn this story
  4. temporary sheet pile wallSterk BVIn this story
  5. architectLEVS architectenMentioned in Converting an old shopping centre into a multifunctional urban district
  6. precast concrete floor slabsDe Hoop PeksoMentioned in Semi-precast floor slabs on demand

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectHIGH5
  • SubjectModular construction
  • CompanyBonneveld
  • CompanyHBB Groep
  • CompanyHoorne Vastgoed
  • CompanySterk BV
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.