Modular construction

Prefabricated plant rooms for streamlined construction

Text Lieke BousemaImage SolidSKID

Door gebruik te maken van de prefab diensten van SolidSKID is het technische hart van het gebouw al vroegtijdig gereed.
Door gebruik te maken van de prefab diensten van SolidSKID is het technische hart van het gebouw al vroegtijdig gereed.

Eurofins is the global leader in Testing, Inspection & Certification (TIC), providing a comprehensive range of analytical services. Eurofins BioPharma Product Testing Netherlands in Leiden, for example, tests pharmaceutical raw materials, intermediates and finished products. To support future growth and serve customers even more efficiently, the two Leiden sites will be brought together under one roof in 2026. Broekbakema designed a new 11,600-square-metre commercial building for the project at Leiden Bio Science Park, the largest life sciences campus in the Netherlands. Aan de Stegge Twello is responsible for construction, while Barth Installatietechniek is delivering all the building services for the laboratory building. By using SolidSKID’s prefabrication services, the building’s technical hub is ready at an early stage.

The new Eurofins BioPharma Product Testing Netherlands building will accommodate a range of laboratories, support facilities, offices and a parking garage across six storeys. Barth Installatietechniek, like SolidSKID, is part of Barth Installatiegroep. Commissioned by Aan de Stegge Twello, it is engineering and installing the electrical, mechanical and plumbing services for these spaces. Barth Installatietechniek is also responsible for additional laboratory services, including technical gas and demineralised water systems. “We designed the building services over a period of nine months, working as one team with Aan de Stegge Twello, the client and the consultants,” says Karel Barth, Director of Barth Installatietechniek. “SolidSKID was also involved from day one, delivering various prefabrication services for these systems. SolidSKID supplies prefabricated plant rooms and skids to the building services market, with the aim of taking care of every aspect for the installer.”

Complete plant room, delivered in one go

The plant rooms are at the heart of all the building services. They were prefabricated in SolidSKID’s workshop in ’s-Gravendeel, in excellent working and environmental conditions. All prefabricated components were then fully tested, made ready for operation and delivered to the site in Leiden well ahead of schedule. There, they can be connected easily and quickly by just a few installers. SolidSKID’s approach offers a robust response to current challenges in construction, such as the shortage of skilled building services professionals, short construction schedules and constrained urban sites, says Roald Kamp, Project Manager, Skid Construction & Prefabrication at SolidSKID. “It also makes it easier to ensure the quality of the installations. The compact units require minimal transport, which is better for sustainability. They can also be easily replaced in the future.” Like Barth Installatietechniek, other installers can benefit from these unique advantages.

Co-ordinating dimensions, weights and lifting schedules

“The skids allow installation work to start during the shell construction phase,” Barth emphasises. “That was also the approach taken in Leiden. During the preparatory phase, we co-ordinated the dimensions and weights of the skids with the contractor. We also agreed on the best times to lift them into place, as they were installed while the building’s shell was still under construction. This helps keep the work on site running smoothly.” Before delivery, the skids were fully wrapped to protect them from the weather.

Big units

“We delivered eleven skids in total, in a range of sizes and configurations,” says Kamp. “The three largest are up to ten by three metres, weigh up to 7,000 kilos when empty, and are used to generate and distribute heating and cooling. Together, the units have a capacity of 2,500 kW.” SolidSKID designed and modelled the steel framework and lifting points for these skids in-house, using 3D/Revit and Barth Installatietechniek’s schematic diagrams as a basis. “We gave particular attention to potential optimisations. All the skids were supplied with controls and insulation. We also fitted flanges to all pipework up to DN 150, and pressure-tested and flushed it, taking care of the entire process for the installer.”

Redundancy built in

In addition to the three large skids, SolidSKID also built smaller ones, Kamp says. “These included skids for the pump groups, temperature sensors, mixing valves and shut-off valves for the air handling units. Redundancy is built in too, with twin pumps and other components that take over if a system fails.” 

Prefabricate wherever possible

The pipework risers were also prefabricated, along with the skids. In addition, 336 connection kits for the room-level heat emitters were standardised and supplied complete with fittings, including control and balancing valves, ball valves and other components. “All of this is designed to ease the workload for installers on site as much as possible,” Kamp concludes. “It also means the various components can be connected even faster.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow