‘This project is attracting interest’

Text Ramona KezerImage Dekker Kozijnprojecten

Qua voorbereiding en logistiek was het project een uitdaging.
Qua voorbereiding en logistiek was het project een uitdaging.

Airtight, insulated prefabricated timber façades

Dekker Kozijnprojecten is supplying and installing the prefabricated timber façades for the renovation of the Bouwmeesterbuurt in Almere. The company was involved at an early stage of the project to help find the best solution.

Dekker is a regular partner of the project’s main contractor, Dura Vermeer Midden-Nederland, explains Piet van den Berg, project coordinator for work preparation and delivery at Dekker Kozijnprojecten. “They asked us in 2019 to help find the best solution for the maintenance needed in this neighbourhood. The preparatory phase took quite a long time. Essentially, the work involved replacing window frames and repairing façades. The architect involved wanted to retain the Scandinavian look. There was also a desire to raise the homes to a higher energy rating.” 

The façade elements are pre-fitted with window frames.

Less transport and fewer labour hours

Initially, the plan was to remove the old façade cladding, install new insulation and then fit new cladding. But as the project involves a large number of homes, this would have required many transport movements and labour hours. Van den Berg says: “It would also have taken much longer than we had in mind. So we started considering using prefabricated façades with the window frames already installed. The demolition contractor removes the existing façade cladding, and we check the substructure for wood rot and inspect the condition of the membrane. We then install the façade elements. It is a fairly large structural intervention. We worked out the details with the structural engineer.” The new façade elements are airtight, with all the junctions sealed with liquid rubber; the existing structure is also finished with it.

A challenge in terms of preparation and logistics

Once installed, the façade is completely finished. The timber was painted green to achieve a Scandinavian look. Each street also has its own colour for the window reveals and a different type of front door. 

For Dekker Kozijnprojecten, this project is certainly not standard work. “Preparation and logistics were quite a challenge. We received excellent support from Bouwburo, which supplied the drawings. We currently have a regular crew of sixteen to eighteen people on site, and we are working at a good pace: we install five elements a day, including the associated work.” Van den Berg sees a future in prefabricated construction and making homes more sustainable. “We also notice that people from all sides are taking an interest in this project. There are a great many homes of this type in the Netherlands. And because the project is going well, the same approach could soon
be used on many more homes.” 

Question about this story? Ask your question

Who worked on it

Bouwmeesterbuurt in Almere, renovatie

  1. main contractorDura Vermeer Midden-Nederland

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectBouwmeesterbuurt
  • SubjectModular construction
  • CompanyDura Vermeer Midden-Nederland
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.