Haga-Leyenburg | Car parks make way for a vibrant residential community

In The Hague, demand for housing continues to rise. Ideally, homes where people can live comfortably well into old age. To meet this demand, the Municipality of The Hague is replacing car parks with more than 600 new homes, commercial facilities and a multi-storey car park at HagaZiekenhuis in The Hague. ‘What an improvement for this area. Just compare those bleak car parks with such a beautiful, vibrant environment.’
Mix and match
To appeal to a range of residents, the ‘Haga-Leyenburg’ project offers a mix of family homes and apartments for sale and rent. 41 family homes have now been completed, and 464 apartments are currently under construction. Below ground, there will be a public two-storey car park. At ground level, there will be a car park for residents and commercial units, with a roof garden on the first floor and apartments on the floors above. Heijmans is delivering the entire area development in partnership with the municipality.
Challenging stakeholder management
During construction, Heijmans has to work with many different parties. A show apartment needs to be fitted out for prospective tenants, and buyers need to be kept informed digitally. Diversions have to be arranged for the heavy car, tram and bus traffic converging at the nearby public transport hub. Local residents need to be kept informed about the progress of the construction work. “You can imagine why we entrusted this complex puzzle to a professional, experienced stakeholder manager and the construction team,” says Harry Verheij, project developer at Heijmans.

The highest point has been reached. The structural shell was completed at the end of 2019.
Vibration-free piling
The hospital is one party that must not be affected by the construction work. It has to remain fully operational at all times. Ambulances must be able to respond at any moment, as must the trauma helicopter, even when six tower cranes are in operation. “At first, conventional piling seemed likely to cause only noise nuisance,” says Verheij. “But during eye surgery, vibrations caused problems during the demolition of the nurses’ residence. So we switched to cast-in-situ piles. First, we push a casing into the ground, then fill it with concrete and reinforcement. The casing is then withdrawn. The sheet piles for the underground car park were also formed in the ground.”
International workforce
Another challenge is staffing the site. “At the moment, finding skilled workers is a real challenge. There are already six nationalities working on this project alone. You have to explain to all of them that safety is a top priority, which means helmets are compulsory. We use pictograms as much as possible to get the message across.”
The most efficient sequence
To meet the deadline, Heijmans is working as efficiently as possible. It groups together homes built using the same construction system. “The tunnel-form homes are being built in one sequence, while the homes with wide-slab floors and walls are in another. The system determines the order in which we work. We’re also on track. The highest point has been reached and the structural shell is due to be completed around the end of 2019. Finishing work has already started in several areas.”
A business enquiry for Heijmans? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHaga-Leyenburg
- SubjectResidential and non-residential construction
- CompanyHeijmans