Residential and non-residential construction

A logistical feat

Text Patricia van der BeekPhotography Martijn Pauw, Asschert Group

A logistical feat

As a supply chain partner to Nijhuis Bouw, Weijerseikhout is carrying out the complete roof renovation at De Donken in Apeldoorn.

The roofs of more than 300 homes are being insulated and largely replaced. As well as presenting an ecological challenge, this project is above all a logistical feat.

“As roofing specialists, we bring technical expertise and process knowledge to the supply chain,” says Bas van Deinsen, commercial manager at Weijerseikhout. “With this in mind, Nijhuis Bouw involves us in its projects from the pre-construction phase.” Sjacó Hendriks, technical energy adviser at Weijerseikhout, adds: “One important consideration during the pre-construction phase at De Donken was flora and fauna. At the request of the ecologist involved in the project, we devised a structure that would allow bats to build their nests. This meant we had to retain part of the roofs and insulate them using a different method.”

Roofing work in progress.

Difficult to access

Weijerseikhout is removing the existing roofs while retaining the roof decking. New insulation, battens, roof tiles, cladding, gutters, roof windows and escape hatches are then being installed. Once the renovation work is complete, the roofs will have an RC insulation value of 6.0 m²K/W. Hendriks says: “The complexity of this project lies in how difficult the site is to access. The streets here are narrow, with cars parked on both sides. That means we have to carefully plan and coordinate our deliveries, often involving heavy equipment. We also cannot simply position the crane anywhere, even though it needs to reach roofs at different heights.”

‘The complexity of this project lies in how difficult the site is to access’

Under control

“There is a lot to consider when renovating a roof,” Van Deinsen adds. “During the design phase, we have to deal with matters such as flora and fauna, fire safety, environmental permits and other municipal procedures. During construction, we depend on the weather. At the same time, the roofing work is the backbone of the construction process. If our work is halted, for example by strong winds, that affects the progress of the project. It is important to think this through and communicate with one another in advance. In that respect, Nijhuis Bouw is a good client and partner: it plans ahead and keeps the processes firmly under control. They deserve credit for that.”

In full swing

Renovation of the roofs at De Donken is in full swing. Van Deinsen and Hendriks have now handed the project over to their colleague Oscar Rietman, who is overseeing the work. “To ensure a smooth handover, we involved Oscar from the pre-construction phase,” says Hendriks. “He also drew on his practical experience to help us think through the logistics.” Van Deinsen adds: “The work is progressing entirely according to plan. We are confident that it will be completed in May this year.”  

Building materials delivered ‘green’ and ‘lean’
On behalf of Nijhuis Bouw, Raab Karcher is supplying all the building materials for the façade and interior renovation at De Donken in Apeldoorn. The building materials specialist is also ensuring smooth logistics on site. “We worked with Nijhuis Bouw from an early stage to find efficient, fire-safe and sustainable solutions for the building materials,” says Paul Meulman, branch manager at Raab Karcher Apeldoorn. “Almost all the materials we supply also carry our Greenworks sustainability label.” For the façade renovation, Raab Karcher is supplying around 6,000 m² of cladding, including battens and insulation. For the interior renovation, it is supplying around 250 kitchens, custom-made trim and Keratop elements for the bathrooms.

One lorry movement per day
Meulman says: “Through our Leanworks logistics service, we are helping to meet an important goal. To minimise disruption for residents, there can be only one lorry movement in the neighbourhood per day. We drive to the project site every day with the materials needed. There, we first collect some products that Nijhuis Bouw cuts to size in what is effectively a cutting shed. We then take everything to the location where it will be installed that same day.” Deliveries are running smoothly, which Meulman says is partly thanks to the excellent cooperation with Nijhuis Bouw and the other parties. “We are confident that the project will be completed successfully.”

Question about this story? Ask your question

Who worked on De Donken

  1. contractorNijhuis Bouw B.V.Mentioned in Building at high speed, with residents’ interests at the heart of the project
  2. housing associationMooilandMentioned in Building at high speed, with residents’ interests at the heart of the project
  3. architectGAAV ArchitectenMentioned in Building at high speed, with residents’ interests at the heart of the project
  4. roofing specialistWeijerseikhoutIn this story

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectDe Donken
  • SubjectResidential and non-residential construction
  • CompanyWeijerseikhout
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.