Preparing homes for district heating

Schiedam has set itself the goal of making the Groenoord neighbourhood completely gas-free. There are still a number of steps to take. The homes need energy-efficiency improvements, and their systems must be made ready for connection to the district heating network. 

Housing association Woonplus awarded the work to Hemubo Bouw, which carried out the first ‘energy makeover’ in the 1970s apartment block in January 2022. The homes had already been partially insulated. Hemubo’s task is to install the pipework needed to connect them to the district heating network, and to fit the windows and doors with HR++ glazing. Its teams will be in each home for no more than ten days.

Winning residents over

As attractive as becoming independent of gas may be in the current climate, residents of Groenoord are sceptical about everything that is planned. “It’s a collective undertaking,” says Michael van Leyenhorst, manager at Hemubo Bouw. “That gives rise to doubts and fears, which residents often reinforce in one another. To build trust, we have set up a six-person resident liaison team together with client Woonplus. The resident support officers take people to the show home, show them what things will look like and let them experience it for themselves, and explain the benefits.” 

The windows and doors are being fitted with HR++ glazing.

Minimising disruption

Installing the new pipework in the gallery-access flats is a major undertaking. Drilling causes noise for two days. Construction workers are in residents’ homes for five days, and temporary facilities are provided to replace the existing heating and water services. “We do everything we can to minimise disruption. Normally, we stick to a tight Lean schedule, but here we have built in rest periods. There are also fourteen respite homes where residents can take a breather. They can have a coffee and a chat there.”

Managing asbestos

The asbestos present in the walls of the homes requires particular attention. Hemubo is doing everything it can to limit the risks through thorough risk assessments and preparation. Tradespeople receive daily briefings to safeguard their own safety and that of the residents. “That takes considerable discipline. But fortunately, things have gone well so far.” 

Supply problems

A different kind of challenge is posed by difficulties in obtaining materials and price rises resulting from the war in Ukraine. To limit these risks, large orders and ample reserves are essential. “We have the space to build up a buffer and the fleet to transport components to the construction site.” 

Hemubo will complete the project in December 2024, leaving residents with safer, more comfortable homes featuring, among other things, new radiators, better heat retention and more hot water from the tap.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectResidential and non-residential construction
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.