Residential and non-residential construction

Osdorpplein, Amsterdam | Renovating with 100% recycled uPVC frames

Osdorpplein, Amsterdam | Renovating with 100% recycled uPVC frames

The 1960s homes on Osdorpplein were badly in need of refurbishment. Housing association Stadgenoot therefore commissioned work to bring them up to date. Sometimes, the work goes further. For example, the partnership between Hemubo and Schipper Kozijnen has resulted in the first 100% recycled uPVC frames.

Indistinguishable from virgin uPVC

To improve living comfort in the homes on Osdorpplein in Amsterdam, the gable walls are being insulated and clad with brick slips. The frames are being replaced, the access galleries raised and the gallery railings replaced. Inside, the system is being prepared for the replacement of communal boilers with district heating; risers and radiators are being renewed, and mechanical ventilation is being installed throughout. Sanitary fittings will be replaced where necessary. Hemubo Almere is carrying out the renovation work while residents stay at
temporary accommodation.

Recycled material in extruder.

Moving residents by riser

The heating risers determine the sequence of the work in the project plan. Sandra Dekker, technical operations manager at Hemubo, explains: “We ask residents on each riser to move to temporary accommodation for three weeks. They leave their homes as empty as possible, and we lend a hand where needed. We have outsourced the coordination of the moves.”

Specialists in complex housing projects

“We work with Hemubo regularly,” says Jappe Dekker, Head of Business Market Sales at Schipper Kozijnen. “Particularly on complex housing projects where the impact on residents is significant. As one of the largest frame manufacturers in the Netherlands, we do a lot of work for the private market. The knowledge and experience we have built up there over the past decades are increasingly being sought for projects too.”

A challenge for both sides

“Sustainability has played an important role in every project for many years,” Dekker continues. “That suits us. We are open to innovation and like to contribute proactively, from design through to completion.” That was also the case on the Osdorpplein project. The doors’ fresh colours and the prefabricated spandrel panels clad with brick slips give the homes a fresh new look. But this project goes further. The replacement doors, windows and frames are made from 100% recycled uPVC. “The idea came about spontaneously,” says Dekker. “We were really just challenging each other a little. How great would it be to develop frames from 100% recycled uPVC? The real challenge came later, of course. It took a year to produce the profiles to the required quality.”

The renovation is being carried out one riser at a time.

Early 2018

The development of frames from recycled uPVC began with a visit to the Profine Group in Berlin. Schipper Kozijnen took Hemubo to meet its main supplier. “The idea of doing more with circularity and sustainability had already come up several times. But over drinks at the end of our factory visit, we simply had the cheek to ask, ‘Why don’t you make profiles from 100% recycled PVC?’ They were initially cautious, but we kept urging them to ‘just’
give it a try.”

Breakthrough in 2019

It would be almost a year before the first samples were delivered to the Schipper Kozijnen factory. During that year, all sorts of designs were developed, tested and tried out. “The colour varied wildly,” Dekker recalls. “It swung between grey, brown, greenish, pale pink and everything in between. To show that the material could indeed be given a neat finish, we applied a proCoverTec coating to half of the sample.” That proved to be a good move. Hemubo welcomed Schipper Kozijnen’s prototypes with open arms. It immediately wanted to look for clients and suitable projects together. Before long, client Stadgenoot agreed to take part in the innovative experiment.

Ready to scale up

To get housing association Stadgenoot even more enthusiastic about the recycling project, Schipper Kozijnen and Hemubo presented a show home. By then, all the profiles already had their familiar, premium appearance. “An outsider could no longer tell the recycled uPVC from virgin material. That was a really significant step. Recycling is part of who we are. We have made major investments and are now ready to scale up.” At Osdorpplein, Schipper Kozijnen is replacing more than 500 frames. Another project is already in the pipeline. After the 2020 summer building break, it will replace the frames on one of its very first projects with frames made from 100% recycled K-VISION profiles. “What could be better than completing the circle this way?”

Just-in-time deliveries

There is no space around the homes on Osdorpplein to set up a construction site. This calls for creative solutions. Hemubo is building a steel structure over the entrance to support the scaffold and construction hoist. At the tramline turning loop, it is stacking three containers to create a passage for residents. Hemubo already has ready-made solutions for other challenges. Dekker explains: “Construction materials are delivered and collected according to strict just-in-time schedules, for example. It is quite a puzzle, especially as supply-chain partners also have to work to these schedules. The result is that all materials are delivered to each home individually. Site teams receive delivery times on their phones.”

The new normal

Two risers have now been renovated. Schedules have been adjusted slightly because of coronavirus. “If someone falls ill at their temporary accommodation, they need to be able to stay there for another two weeks. We have created this capacity by working on two risers at a time. We are also seeing the new normal becoming well established in the way we work together. People are already keeping 1.5 m apart without even thinking about it.”   

Question about this story? Ask your question

Who worked on it

Stadgenoot's 1960s homes at Osdorpplein in Amsterdam

  1. clientStadgenoot
  2. renovation worksHemubo Almere
  3. window framesSchipper Kozijnen

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectStadgenoot's 1960s homes at Osdorpplein
  • SubjectResidential and non-residential construction
  • CompanyStadgenoot
  • CompanyHemubo Almere
  • CompanySchipper Kozijnen
Share this article