Scaffold-free construction for ‘TwoTwoFive’ apartment block in Amstelveen
Text Tim van DorstenFotografie Heddes Bouw & Ontwikkeling

In Amstelveen, an ageing office building has made way for the construction of the sustainable ‘TwoTwoFive’ apartment block. The decision to build without scaffolding has helped ensure that the first residents can move into their new apartments before the summer.

Around three years ago, property developer and investor Forum Amstelveen Invest asked Heddes Bouw & Ontwikkeling to carry out the construction work on a new apartment block at Biesbosch 225 in Amstelveen. After the North Holland-based construction company had determined the most suitable construction method and optimised the preliminary design for the new residential building, it began work on the three-storey underground car park in early 2020. “We used underwater concrete for this car park,” says Piet Wever, project manager at Heddes Bouw & Ontwikkeling. “We chose this method because the car park is so deep. Amstelveen’s low-lying position means that both groundwater pressure and the groundwater level are relatively high, creating considerable upward pressure. For the building itself, which has a shallow foundation, we devised a flexible structure: the tension piles were given a dual function. As the load from the building on the foundation increases, the tension piles act as flexible piles. This helps reduce settlement and deflection of the raft foundation.”

After completing the car park, Heddes continued work on the 18-storey complex, which contains a total of 276 rental apartments. “Working with architecture firm OZ, we took full responsibility for the construction and delivery of this residential complex,” Wever says. “This means ensuring that the building services are fully designed and drawn up, and involving the subcontractors at an early stage. This has enabled us to deliver the project within the specified time and budget.” The residential building has a system that uses thermal energy storage in the ground, allowing it to be heated and cooled using geothermal energy. This is combined with solar panels. All the apartments are also fitted with a high-efficiency heat recovery system, using CO2-controlled ventilation to maintain indoor air quality.
Scaffold-free
To meet the construction deadline, Heddes Bouw & Ontwikkeling decided to build the storeys without scaffolding. “There isn’t much room on the site to erect scaffolding, and leaving it on the deck for too long would delay the start of the site layout work. So we decided to use fully bespoke elements and balconies for each storey, all complete with balustrades, glazing and window frames,” Wever explains. “These prefabricated elements are delivered to the site ready for installation. We then fit them using hoistable scaffolds positioned on the balconies. This allows us to watch the building rise step by step, fully finished.”

This was the first time Heddes Bouw & Ontwikkeling had opted for scaffold-free construction. It appears to have been a success, as the company is now using the same approach on another project in Amsterdam. “Building without scaffolding means we need less construction time.” By mid-March, the façade was complete, and the company had moved on to fitting out the homes, connecting the sewer and utilities, and landscaping the roof garden above the car park. The first residents are expected to move into their new apartments before the summer of 2022.
Vraag over dit verhaal? Ask your question
Wie eraan werkte
TwoTwoFive in Amstelveen
- projectontwikkelaar en beleggerForum Amstelveen Invest
- bouwbedrijfHeddes Bouw & Ontwikkeling
- architectenbureauarchitectenbureau OZ
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectTwoTwoFive
- OnderwerpResidential and non-residential construction
- CompanyForum Amstelveen Invest
- CompanyHeddes Bouw & Ontwikkeling
- Companyarchitectenbureau OZ