Installing the precast concrete elements became a precision task carried out by hand

Text Liliane VerwooldeImage LEVS architecten

Installing the precast concrete elements became a precision task carried out by hand

Building high-rise without scaffolding

The Ox is a new, stylish apartment building in Osdorp, Amsterdam. The way the building was constructed is surprising. Despite being a substantial high-rise, the entire building rose without scaffolding.

The concrete elements were put in place using two tower cranes and nine mobile elevating work platforms.

From a distance, The Ox looks like a staircase with four steps. The highest step comprises eight storeys, the next has seven, and the number then decreases from six to five. The building, designed by LEVS architecten, contains 168 apartments, 134 of which are in the mid-market rental segment and 34 in the private rental sector. “Demand for affordable housing is enormous in this region,” says Nick Dijkhof, project manager at Van Wijnen. “The apartments in The Ox are therefore a welcome addition to the city of Amsterdam!” The apartments range in size from 58 to 126 m2. Beneath The Ox are a car park and a bicycle storage area. 

Deze afbeelding heeft een leeg alt-attribuut; de bestandsnaam is LEVS_OX-3-1024x683.jpg
The standard of finish in the entrance areas is remarkably high.

Scaffolding-free construction

When the decision was made to build The Ox without scaffolding, this seemed cheaper and easier than using scaffolding. Dijkhof has since revised his view to some extent, although the benefits still stand. “The façades are made up of three layers,” he explains. “The first layer consists of timber-frame elements. This is followed by the insulation layer and, finally, the precast concrete elements. If we had had to install those precast concrete elements through the scaffolding, it would undoubtedly have caused problems. But installing the precast concrete elements this way was also a challenge.”

The façades give The Ox a stunning appearance.

Precision work

Two tower cranes were in place for positioning and installation, along with no fewer than nine mobile elevating work platforms at peak times. The tower cranes lifted the elements into position, after which they were aligned from the platforms. “It was precision work. Our people had to move up and down in the platforms many times, giving the elements just the right nudge to get them hanging in exactly the right position. Naturally, they became more adept at it and the pace picked up, but the challenge was greater than we had anticipated.”

The Ox, an asset to the city.

Dijkhof is nothing but proud of the result. “The façades give The Ox a stunning appearance. The standard of finish in the entrance areas is also remarkably high. The tiling, walls finished ready for painting and dado panelling are all of a high quality. Our people carried out this finishing work while around eighty construction workers were using the same entrance. But that, too, worked out well. The Ox is a magnificent building, an asset to the neighbourhood, the city and its residents.”

Question about this story? Ask your question

Who worked on it

  1. ClientVesteda, Amsterdam
  2. ArchitectLEVS architecten, Amsterdam
  3. ContractorVan Wijnen, Diemen

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectResidential and non-residential construction
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.