Building and renovating while lessons continue as normal

Building and renovating while lessons continue as normal

Gomarus Scholengemeenschap in Gorinchem had outgrown its premises. With the reorganisation of the existing school building and a substantial extension…

Working with respect for one another

Gomarus Scholengemeenschap in Gorinchem had outgrown its premises. The reorganisation of the existing school building and a substantial extension will ensure it meets the school’s needs for the foreseeable future.

Gomarus Scholengemeenschap in Gorinchem had been using temporary premises on Lange Slagenstraat for some time. Now that the existing school is being extended with a new three-storey building, each floor covering around 400 m², the temporary premises can be vacated in September 2019. The daily commute between the two sites will then come to an end, along with the time lost and the various unsafe traffic situations. Part of the existing building is also being reorganised so that the teaching spaces are better suited to the way lessons are delivered. All the construction work is being carried out by Burgland Bouw.

Primary structure

The primary structure of the new building consists of steel and calcium silicate masonry, combined with hollow-core slabs. The external walls are being built in traditional brickwork, with aluminium façade frames. Particular attention has been paid to the entrance, which is being enlarged and given timber cladding to make it more prominent. The new section blends seamlessly with the existing building.

Additional safety measures

“The project is progressing well and does not involve any exceptionally demanding technical challenges,” says Hubert van Velden, project manager at Burgland Bouw. “However, building in and near a school where lessons are taking place as usual calls for a great deal of care. Hundreds of pupils walk and cycle to this school or a nearby one every day. That means taking extra safety measures. We schedule deliveries outside these hours only. We also took the exam periods for the senior classes into account when planning our work. On those days, we worked as quietly as possible.”

Tight deadline

“No, it is not difficult for us to take these things into account,” Van Velden continues. “The school board also takes our needs into account. It has made part of the playground available to us for storing equipment and materials. This makes it easier for us to work. We will hand over the new building to the school just before the autumn half-term break. The space can then be fitted out during the break, after which around 450 pupils from the region can move into their refurbished school in Gorinchem.”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectEducation
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.