Vibration-free screw injection piles installed through bespoke casings

Aurora Amsterdam stands at the intersection of several city districts, with a historic façade and an existing basement. The new extension required a completely vibration-free foundation, installed in an extremely confined space in the heart of the city. A job for Ras Heiwerken.

The Aurora construction site is on what Klaas Ras calls one of Amsterdam’s lifelines. “This is one of the busiest traffic junctions in the city. Space is limited, storage options are scarce and traffic is constantly moving around you.” That makes foundation work especially sensitive. Low-vibration piling with steel tubular piles was not an option. “Because you’re right in the city centre, that’s out of the question.”

Vibration-free work with compact drilling rigs

For Aurora, Ras Heiwerken opted for screw injection piles, installed without vibration using compact drilling rigs. “Given the groundwater level, this type of pile is the best option for this project. They’re also the most sustainable. You can install them with small machines that use little fuel and produce few emissions, yet are powerful enough to drive these heavy piles into the ground.”

A new foundation in an existing basement

One unusual aspect of the project was that the extension is being built on top of an existing basement. “We were working at ground-floor level, but most of the building already had a basement. We made and fitted casings for it, and installed them in the basement. We then installed the piles from above, through the casings.” This was necessary to prevent flooding. “If you drill a hole there without a casing, the basement will fill with water.”

The casings were custom-made for this project at Ras’s own factory. “That’s one of our specialities. We made them ourselves, installed them and removed them again once the work was complete.”

Preparation almost as important as execution

According to Ras, the casings posed the biggest challenge. “They required thorough preparation. Here, that was almost as important as the execution.” Coordination with Van Wijnen and the structural engineer played a major role. “We discussed everything in advance and worked out together how to do the job safely and accurately.”

Despite the complexity, Ras looks back on the work with pleasure. “Projects like these are what keep things interesting. A bit of a challenge, in a location like that, makes it exciting. And we’re always happy to build in urban areas with limited space.”  

Vraag over dit verhaal? Ask your question

Wie aan het Auroragebouw werkte

  1. hoofdaannemerVan Wijnen AmsterdamGenoemd in Basement works lay the foundations for the landmark Aurora renovation
  2. beton- en constructiewerkzaamhedenDe Heeren BouwmeesterGenoemd in Basement works lay the foundations for the landmark Aurora renovation
  3. installatiesBuilding Services AmersfoortGenoemd in Iconic office building gets a new lease of life
  4. volglazen videGlass InsideGenoemd in A glass void gives Aurora a new look
  5. voorzieningen voor gierzwaluwenVivara ProGenoemd in Renovating while making room for protected species
  6. netbeheerderLianderGenoemd in Iconic office building gets a new lease of life
  7. aannemerVan WijnenGenoemd in A glass void gives Aurora a new look
  8. funderingswerkRas HeiwerkenIn dit verhaal

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectAuroragebouw
  • OnderwerpGeneral
  • BedrijfRas Heiwerken
Deel dit artikel

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.