General

Excavation of all cofferdams at De Groene Boog

Text Roel van GilsImage Verboon Maasland

Uiteindelijk werden de ‘specials’ rondom De Rotte nog wel met draglines ontgraven, maar voor het grootste deel werd gekozen voor hydraulische kranen vanaf pontons.
Uiteindelijk werden de ‘specials’ rondom De Rotte nog wel met draglines ontgraven, maar voor het grootste deel werd gekozen voor hydraulische kranen vanaf pontons.

A complex challenge successfully completed

Excavating the cofferdams for the new A16 Rotterdam was a major operation involving complex challenges. With 34 cofferdams in total, some requiring highly specialised work around closely spaced piles and struts in confined working areas, the project called for specialist techniques and meticulous planning. Commissioned by the De Groene Boog consortium, Verboon Maasland contributed to large-scale and specialist earthworks for more than 2.5 years.

Well before the project began, Van Oord, a fellow consortium partner, approached Verboon Maasland to discuss the excavation of the cofferdams. “Initially, the plan was to use cable excavators throughout the project, but it soon became clear that this was not technically feasible,” says Sjors Kouwenhoven, site supervisor at Verboon Maasland. “The cable excavators would have put too much pressure on the sheet-pile walls, and in many cases there was less space available than originally estimated. In the end, the ‘specials’ around De Rotte were still excavated using draglines, but hydraulic excavators working from pontoons were chosen for most of the work.”

Verboon Maasland gained valuable experience here, which will also prove useful on other projects.

Grabbing or suction dredging

With 34 cofferdams in total, the project posed a considerable challenge: each one had its own specific requirements and approach. “The cofferdams around De Rotte were particularly complex, with numerous struts and limited working space,” Kouwenhoven recalls. “Rather than grabbing the soil, we carefully washed it away and suctioned it up to prevent damage to the piles and the riverbed. We used this technique around the piles in all the other cofferdams too, but most of the excavation was carried out ‘traditionally’, underwater using a grab.” The equipment used varied considerably, with peak periods when Verboon Maasland deployed three cable excavators and two crawler excavators at the same time. “We also had to hire in a lot of equipment, as we were working on the A24 Blankenburgverbinding at the same time.”

Kouwenhoven says that, aside from the technical challenges, the schedule was also demanding. “A lot of diving work was required, and this often ran over while the deadlines remained unchanged. It was up to us to respond flexibly, which is something we’re well equipped to do.” Verboon Maasland and Van Oord shared equipment and work, resulting in a good working relationship that continued after the project was completed, with ongoing contact and follow-up commissions. “We also gained valuable experience here, which will prove useful on other projects.” 

Question about this story? Ask your question

Who worked on A16 Rotterdam

  1. construction consortiumDe Groene BoogMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  2. construction consortiumBESIXMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  3. construction consortiumDura VermeerMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  4. construction consortiumVan OordMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  5. construction consortiumCroonwolter&drosMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  6. construction consortiumMobilisMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  7. earthworksVerboon MaaslandIn this story
  8. main contractorTBIMentioned in Geotechnical precision beneath the A16 Rotterdam

Keep following this

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

What you follow
  • ProjectA16 Rotterdam
  • SubjectGeneral
  • CompanyVerboon Maasland
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.