Construction projects

Geotechnical precision beneath the A16 Rotterdam

Text Frederique HutingImage Rob van Buuren en Michel de Koning

Aanbrengen damwanden aan de westzijde van de Rotte (Beeld: Michel de Koning)
Aanbrengen damwanden aan de westzijde van de Rotte (Beeld: Michel de Koning)

Getting to grips with the ground

The construction of De Groene Boog places high demands on everything that happens below ground level. CRUX joined the project as geotechnical consultant in late 2018, making an essential contribution to the design and construction of the tunnel crossing regional flood defences, earthworks, civil engineering structures and temporary structures.

Working for the main contractors BESIX, Dura Vermeer, Van Oord and TBI, CRUX was closely involved in the project from the preliminary design stage. “We started during the preliminary design phase with a team of six consultants and have remained closely involved from the outset,” says Johan Zwaan, senior specialist and partner. “From the detailed design phase onwards, our focus was on sections 2 and 3, which included the Rottemerentunnel, earthworks, adjacent civil engineering structures and temporary bridges. Colleagues also worked on section 1, which runs roughly from the Rijksweg A13 to the northern approach to the Rottemerentunnel.”

Stability and flood safety

The tunnel passes beneath the Rotte and the Vaart Bleiswijk, among other waterways. “Earthworks had to be built above and alongside it, as well as cycle paths, temporary structures and the redeveloped Lage Bergse Bos, all of which interacted with the tunnel structure,” explains Michel de Koning, senior geotechnical consultant. “Because the dykes along the Rotte and the Vaart Bleiswijk serve as regional flood defences, stability and flood safety were crucial. And as the work took place right next to residential areas, its impact on the surrounding area also had to be kept to a minimum.”

Weak ground and a tight schedule

The ground conditions made the work even more challenging. “In section 2, we encountered one of the weakest and most variable soil profiles we have ever seen,” says De Koning. “We commissioned extensive additional investigations to ensure we had a sufficiently reliable basis for our designs.” For example, the ground contained sand lenses that affect groundwater levels and had to be mapped in detail through further investigation. Such details can make the difference between a robust design and a risky one.

Pile foundation for pile cap, Kunstwerk 52A. (Image: Rob van Buuren)

Coordination and collaboration

In section 3, CRUX designed, among other things, a piled embankment over which the 450-metre flyover was slid across the A20. “This required careful coordination between the abutment, piled embankment, sheet piling, temporary construction roads and permanent embankments,” says Zwaan. “The raising of the ground, installation of piles and construction of the foundation piers had to be carried out largely in parallel, placing high demands on the coordination of the phasing, the interaction between the structures and overall project management.”

Daily coordination with the consortium and Rijkswaterstaat during the Covid-19 pandemic was also a notable aspect of the project. Zwaan says: “Much of the consultation took place online, and we had to process updates on progress, monitoring data, risks and design changes quickly. CRUX’s role was both advisory and collaborative: we translated complex ground and monitoring data into designs that could be built.”

Applied expertise

CRUX remained actively involved during construction. “Among other things, we designed the working platforms for foundation equipment, based on a new guideline that was being applied on a large scale for the first time,” says De Koning. “Combined with the soft ground, this presented a considerable design and construction challenge.”

Confidence below the surface

Drawing on broad expertise in geotechnical engineering, geohydrology, environmental impact and ground improvement techniques, CRUX delivered carefully considered solutions for a complex subsurface. Zwaan says: “A design that can be built and takes the surrounding area into account. That’s where our strength lies.”  

Question about this story? Ask your question

Who worked on A16 Rotterdam

  1. construction consortiumDe Groene BoogMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  2. construction consortiumBESIXMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  3. construction consortiumDura VermeerMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  4. construction consortiumVan OordMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  5. construction consortiumCroonwolter&drosMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  6. construction consortiumMobilisMentioned in A16 Rotterdam: 11 km-long energy-neutral motorway
  7. earthworksVerboon MaaslandMentioned in Excavation of all cofferdams at De Groene Boog
  8. main contractorTBIIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • SubjectConstruction projects
  • CompanyTBI
Share this article

Advertisement

Follow on Stedenbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.